View allAll Photos Tagged Unloading

Tons of tetrapak is coming everyday.

CEA were employed by CATERPILLAR Thailand to unload and transfer welding machines & other equipment at their UGM plant in Chonburi.

Assistant Yard Manager Virasak Sriboon began the project by holding a toolbox talk and joint hazard analysis (JHA) meeting with his teams.

Trucks and their cargo formed a queue and one by one pulled alongside a CEA 55 ton crane to begin unloading. The CEA team removed all lashing straps and attached the crane slings to the cargoes. The crane lifted the cargoes on to an awaiting 25 & 15 T forklifts. The forklifts transported the cargo to the Caterpillar storage area, a CEA banksman supervised all movements.

Day 2

CEA teams unloaded cargo crates from 40ft Containers at their respective cargo docks, a 3 ton forklift was used to place the crates on wooden pallets for easier storage, once again the cargo was transported to the storage area.

All scrap material left over from the project was cleared for disposal. Flat rack containers used in the operation were stacked on to one lowboy trailer. General housekeeping was carried out in the working areas.

All CEA equipment was demobilized and readied for transport back to the operations base in Laem Chabang.

 

Teamwork concept. Isolated on white

Unloading spares for No. 21, New Norfolk, 2001. Spare Paxman V12 engine. David Lidster photo

www.dvr.org.au

www.facebook.com/pages/Derwent-Valley-Railway-Tasmania/12...

from the ship Emssky at the new pier for the Fortum KVV8 heat- and powerplant in Stockholm, Sweden.

Cumberland Mine loadout. A train being unloaded. A better look at where the hoppers are dumped.

CEA were employed by CATERPILLAR Thailand to unload and transfer welding machines & other equipment at their UGM plant in Chonburi.

Assistant Yard Manager Virasak Sriboon began the project by holding a toolbox talk and joint hazard analysis (JHA) meeting with his teams.

Trucks and their cargo formed a queue and one by one pulled alongside a CEA 55 ton crane to begin unloading. The CEA team removed all lashing straps and attached the crane slings to the cargoes. The crane lifted the cargoes on to an awaiting 25 & 15 T forklifts. The forklifts transported the cargo to the Caterpillar storage area, a CEA banksman supervised all movements.

Day 2

CEA teams unloaded cargo crates from 40ft Containers at their respective cargo docks, a 3 ton forklift was used to place the crates on wooden pallets for easier storage, once again the cargo was transported to the storage area.

All scrap material left over from the project was cleared for disposal. Flat rack containers used in the operation were stacked on to one lowboy trailer. General housekeeping was carried out in the working areas.

All CEA equipment was demobilized and readied for transport back to the operations base in Laem Chabang.

 

Southwest Airlines Boeing 737-7H4 (N428WN) at Manchester-Boston Regional Airport (MHT), Manchester, NH

 

- - - - -

 

Blogged by The Consumerist ("Southwest Pilot Wishes Happy Birthday To 'Mom On Board,' Passengers Hear 'Bomb On Board'" by Chris Morran - February 27, 2012) at consumerist.com/2012/02/southwest-pilot-wishes-happy-birt...

One of the first things Charlie Bradshaw did on taking over the Silverton Branch was to order the removal of the fake stacks off the 470s. Two of these survived to become pieces of artwork along side the new river walk trail in Silverton in 2012.

Everyone from kids to moms to guys riding motorcycles helped us load and unload the trucks.

CEA were employed by CATERPILLAR Thailand to unload and transfer welding machines & other equipment at their UGM plant in Chonburi.

Assistant Yard Manager Virasak Sriboon began the project by holding a toolbox talk and joint hazard analysis (JHA) meeting with his teams.

Trucks and their cargo formed a queue and one by one pulled alongside a CEA 55 ton crane to begin unloading. The CEA team removed all lashing straps and attached the crane slings to the cargoes. The crane lifted the cargoes on to an awaiting 25 & 15 T forklifts. The forklifts transported the cargo to the Caterpillar storage area, a CEA banksman supervised all movements.

Day 2

CEA teams unloaded cargo crates from 40ft Containers at their respective cargo docks, a 3 ton forklift was used to place the crates on wooden pallets for easier storage, once again the cargo was transported to the storage area.

All scrap material left over from the project was cleared for disposal. Flat rack containers used in the operation were stacked on to one lowboy trailer. General housekeeping was carried out in the working areas.

All CEA equipment was demobilized and readied for transport back to the operations base in Laem Chabang.

 

An Eddie Stobart (Autologic) trucker unloading a Toyota in Newport, South Wales.

Waverley Route Heritage Association.

16th April, 2012.

Osowski Ag - St. Francis, Kan.

Unloading the Samba crane from Lyttelton on to Bledisloe wharf.

June 1986

The "Volcan de Tindaya" just arrived from Lazarote to Fuerteventuras port of Correlejo.

Collage for latest theme at The Kollage Kit =

 

kollagekit.blogspot.com/

Time to unload the fish from the boat. Photographed at the fisheries wharf, Kota Kinabalu.

 

#201009-44 ~Lightbox~

 

smc Pentax-A 1:1.4 50mm.

A dredging operation taking place on the Grand Union Canal at Old Linslade. The actual dredging was taking place in the winding hole close to Bridge 110. The loaded mud hoppers were then moved by a pusher tug to an unloading site just to the north of Broad Oak Bridge (Bridge 109). There the dredgings were unloaded, screened and then spread on the fields between the canal and the River Ouzel.

Unloading gravel at Shipley Wharf in April 1977.

CEA were employed by CATERPILLAR Thailand to unload and transfer welding machines & other equipment at their UGM plant in Chonburi.

Assistant Yard Manager Virasak Sriboon began the project by holding a toolbox talk and joint hazard analysis (JHA) meeting with his teams.

Trucks and their cargo formed a queue and one by one pulled alongside a CEA 55 ton crane to begin unloading. The CEA team removed all lashing straps and attached the crane slings to the cargoes. The crane lifted the cargoes on to an awaiting 25 & 15 T forklifts. The forklifts transported the cargo to the Caterpillar storage area, a CEA banksman supervised all movements.

Day 2

CEA teams unloaded cargo crates from 40ft Containers at their respective cargo docks, a 3 ton forklift was used to place the crates on wooden pallets for easier storage, once again the cargo was transported to the storage area.

All scrap material left over from the project was cleared for disposal. Flat rack containers used in the operation were stacked on to one lowboy trailer. General housekeeping was carried out in the working areas.

All CEA equipment was demobilized and readied for transport back to the operations base in Laem Chabang.

 

CEA were employed by CATERPILLAR Thailand to unload and transfer welding machines & other equipment at their UGM plant in Chonburi.

Assistant Yard Manager Virasak Sriboon began the project by holding a toolbox talk and joint hazard analysis (JHA) meeting with his teams.

Trucks and their cargo formed a queue and one by one pulled alongside a CEA 55 ton crane to begin unloading. The CEA team removed all lashing straps and attached the crane slings to the cargoes. The crane lifted the cargoes on to an awaiting 25 & 15 T forklifts. The forklifts transported the cargo to the Caterpillar storage area, a CEA banksman supervised all movements.

Day 2

CEA teams unloaded cargo crates from 40ft Containers at their respective cargo docks, a 3 ton forklift was used to place the crates on wooden pallets for easier storage, once again the cargo was transported to the storage area.

All scrap material left over from the project was cleared for disposal. Flat rack containers used in the operation were stacked on to one lowboy trailer. General housekeeping was carried out in the working areas.

All CEA equipment was demobilized and readied for transport back to the operations base in Laem Chabang.

 

A dredging operation taking place on the Grand Union Canal at Old Linslade. The actual dredging was taking place in the winding hole close to Bridge 110. The loaded mud hoppers were then moved by a pusher tug to an unloading site just to the north of Broad Oak Bridge (Bridge 109). There the dredgings were unloaded, screened and then spread on the fields between the canal and the River Ouzel.

The unloading site for the Tarago Garbage Train. Originally run for Collex, the train is now operated Veolia, from Clyde Yard (Sydney) to this intermodal yard just past Tarago Station.

 

The train from Sydney arrives six days a week and splits up upon arrival to the siding. All the wagons are unloaded one by one, their containers being transferred to road trucks to be taken the rest of the way to the mine where the garbage is dumped.

CEA were employed by CATERPILLAR Thailand to unload and transfer welding machines & other equipment at their UGM plant in Chonburi.

Assistant Yard Manager Virasak Sriboon began the project by holding a toolbox talk and joint hazard analysis (JHA) meeting with his teams.

Trucks and their cargo formed a queue and one by one pulled alongside a CEA 55 ton crane to begin unloading. The CEA team removed all lashing straps and attached the crane slings to the cargoes. The crane lifted the cargoes on to an awaiting 25 & 15 T forklifts. The forklifts transported the cargo to the Caterpillar storage area, a CEA banksman supervised all movements.

Day 2

CEA teams unloaded cargo crates from 40ft Containers at their respective cargo docks, a 3 ton forklift was used to place the crates on wooden pallets for easier storage, once again the cargo was transported to the storage area.

All scrap material left over from the project was cleared for disposal. Flat rack containers used in the operation were stacked on to one lowboy trailer. General housekeeping was carried out in the working areas.

All CEA equipment was demobilized and readied for transport back to the operations base in Laem Chabang.

 

The ELR JCB unloads some concrete sleepers to replace the wooden ones.

1 2 ••• 25 26 28 30 31 ••• 79 80