View allAll Photos Tagged officespace

Aerial photographs of the construction of the New Village Development.

 

For more information on this project please visit www.newvillagepatchogue.com

For more information about TRITEC please visit www.tritecrealestate.com

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

empty building for start ups in Lyon (now crowded)

Photos of the larger office (available for rent as of December 1st, 2010) at The Network Hub, 422 Richards Street, Third Floor, downtown Vancouver.

Location, location, location. Where you rent office space can make or break your business. Our office space for rent is furnished, equipped and staffed. Great for professionals and solo-preneurs – focus on what raises revenue and leave the rest to us. Learn more at www.virtualofficestaff.com or call 973-509-4632

  

Since our last photo…

 

Building 3 is formed for the first phase of elevated structural concrete deck, and the second phase elevated deck pour will be moving toward the Lake Street edge by the end of July.

 

Building 4 has much of its sub grade structure in place with a move toward the elevated structural deck by the end of August.

 

Subgrade utilities for LIPA, Verizon and Cablevision are completed at 70% of the site along with the same percentage of sewer and storm connections to on site drainage structures.

 

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

posted on Chic Modern Vintage Feb 7, 2011.

These are photos of the C3 Co-Working space at the Cambridge Innovation Center in Cambridge, MA.

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

The Provision office has many whiteboard walls and tables to encourage collaboration, teamwork and creative thinking.

...I'm gonna need you to come in on Saturday.

We do find time to work.

These are photos of the C3 Co-Working space at the Cambridge Innovation Center in Cambridge, MA.

Full time, part time or as you need it office space for rent. Full time office for rental packages come furnished equipped and staff. Virtual office programs allow you to rent office space as you need it and only when you need it. Keep your fixed overhead as low as possible for as long as possible. Great for professionals and solo-preneurs. Learn more at www.virtualofficestaff.com or call 973-509-4632

  

This is what it looks like when Toyland throws up.

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

Location, location, location. Where you rent office space can make or break your business. Our office space for rent is furnished, equipped and staffed. Great for professionals and solo-preneurs – focus on what raises revenue and leave the rest to us. Learn more at www.virtualofficestaff.com or call 973-509-4632

  

Since our last photo…

 

Building 3 is formed for the first phase of elevated structural concrete deck, and the second phase elevated deck pour will be moving toward the Lake Street edge by the end of July.

 

Building 4 has much of its sub grade structure in place with a move toward the elevated structural deck by the end of August.

 

Subgrade utilities for LIPA, Verizon and Cablevision are completed at 70% of the site along with the same percentage of sewer and storm connections to on site drainage structures.

 

Collection & Resource Management office suite

This is a great day. My desk is usually piled with tons of clutter and chaos. I'm also guessing the mess is close to godliness.

 

The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

Bright, open, move-in condition loft space available in well-managed, boutique loft building located on Broadway just steps from Houston Street in Manhattan's bustling SoHo neighborhood. Space features exposed ceilings, hardwood floors, western light/views, exposed brick walls and is configured with a pantry and open bullpen. Space measures 3,984 sf and asking rent is $55.00/sf, $18,260/month.

My boys have quite a few Anime' posters in their Teen Suite and have begged me since we bought our house to paint the walls to coordinate with their posters.

 

So I have procrastinated for 2.5 yrs and I am tired of looking at the builders white walls but have no clue which color to settle with. Whatever I select has to blend in with my office since they are in close proximity.. hmmm I just dunno

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

"Uh-oh. Sounds like somebody's got a case of the Mondays."

Photos of the larger office (available for rent as of December 1st, 2010) at The Network Hub, 422 Richards Street, Third Floor, downtown Vancouver.

meeting room space at Abbey Business Centres in London EC3

@ Panic (rooftop level)

Since our last photo…

 

Building 3 is formed for the first phase of elevated structural concrete deck, and the second phase elevated deck pour will be moving toward the Lake Street edge by the end of July.

 

Building 4 has much of its sub grade structure in place with a move toward the elevated structural deck by the end of August.

 

Subgrade utilities for LIPA, Verizon and Cablevision are completed at 70% of the site along with the same percentage of sewer and storm connections to on site drainage structures.

 

1 2 ••• 40 41 43 45 46 ••• 79 80