View allAll Photos Tagged sitework

Granada Village Shopping Center Redevelopment (Building A1 Roof Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.

My beautiful picture

$6 million, 10,500 sf ground-up construction of a new chapel and meeting area; scope of work included sitework, landscaping, limestone and granite veneers imported from Jerusalem, structural steel, fritted glass wall, slate roof, millwork, ceramic tile, wood flooring, and acoustical ceilings

Truck 177, a Peterbilt 330 belonging to Pioneer Sand Company. Not sure about the specs on this one, but the motor appears to be smaller than the Cat C10s in trucks 130 and 129, and it turns about 2000 RPMs at 60 MPH.. so it's geared more like a sitework truck, but isn't powered like one. Not to mention that the cab is a bit on the cramped side, with the turn signal lever perfectly positioned to be bumped by my right knee whenever I use the clutch, and the snowplow control positioned perfectly to be bumped by my right knee quite often.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.

Visit us at www.bigiron4sale.com

Granada Village Shopping Center Redevelopment (Existing Pad I/J Demolition - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A2 Roof Construction - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.

England Drive Subdivision in Alexandria, Louisiana.

Granada Village Shopping Center Redevelopment (Building A3 & A4 Roof Construction - 2012-02-09) - Granada Hills, CA. Urban One www.urbanone.com.

Cherokee Apartments in New Iberia, Louisiana.

My beautiful picture

so, all of this latest upload is taken from a recently cleared site.

the Lantana bushes (declared noxious weed, therefore the manager is legally bound to eradicate) were killed with roundup brashing, a technique quite effective, which basically consist of 'painting' a few branches of the bush with one of the most potent poison out there, the Monsanto's Roundup (the main active ingredient is glyphosate).

We dont wonna go Monsanto's way, but take back the focus on those species, basically after the lantana was killed and ripped out of the dirt a number of regeneration species (natives have been planted, some survived some not, but all around them a new set of pioneer came in to help heal the land, like inkweed, nettle, thistle, dock etc..

Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.

Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.

Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.

Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.

 

Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-08) - Granada Hills, CA. Urban One www.urbanone.com.

skinning the tree

 

the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:

bnstudio.com.au/page/

 

The project was supported by Bundanon Trust

and produced as part of SiteWorks:

www.bundanon.com.au/content/siteworks-canoe

This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

tarred & backfilling

My beautiful picture

Project Description:

 

Complete siteworks include clear and grubbing, rock blasting, large steel and HDPE pipe installation.

 

Plant includes 500,000 gallons concrete clearwell, 4 filter cells – 107,000 sq. ft., a separate Chlorination Building, as well as a Control Valve Building.

 

Construction of the WWTP included diverting a creek , which ran directly through the site. All environmental work had to meet strict DFO standards.

   

The Westpro Advantage:

 

All earthworks were coordinated on a very confined site and executed with Westpro forces.

 

The 20,000 m3 of filter sand was screened and washed on site to alleviate costly and time consuming trucking off and back to site.

 

7/9/2015: Sitework to connect wastewater infrastructure and installation of new manholes.

Project Description:

 

This secondary school includes metal and built up roofing systems, masonry, stucco and metal panel exteriors, irrigated playfields concrete paved courtyards, gymnasiums, cafeteria, library, technical shops, computer and science labs.

 

The work included extensive sitework, clearing and grubbing and off site services.

   

The Westpro Advantage:

 

Our ability to handle the complete range of requirements for the project, excavating, sewer, water and interior architectural finishing, ensured that the work was completed in the expected and required time frame.

 

Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 DIning District Sitework Construction - 2012-02-24) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2012-01-25) - Granada Hills, CA. Urban One www.urbanone.com.

Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.

Visit us at www.bigiron4sale.com

Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.

Visit us at www.bigiron4sale.com

Parked up, waiting to be escorted into the siteworks, of the rapid rail uploading project.

My beautiful picture

soaking of bark

  

the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:

bnstudio.com.au/page/

 

The project was supported by Bundanon Trust

and produced as part of SiteWorks:

www.bundanon.com.au/content/siteworks-canoe

the fold

  

the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:

bnstudio.com.au/page/

 

The project was supported by Bundanon Trust

and produced as part of SiteWorks:

www.bundanon.com.au/content/siteworks-canoe

Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.

Visit us at www.bigiron4sale.com

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Granada Village Shopping Center Redevelopment (Phase 2 Dining District Sitework Construction - 2012-01-27) - Granada Hills, CA. Urban One www.urbanone.com.

Single family homes in Baton Rouge, Louisiana.

1 2 ••• 5 6 8 10 11 ••• 78 79