View allAll Photos Tagged sitework

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Somebody Had to Do It" was performed and installed at the Iribe Building. Photos: Jelena Dakovic.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

Michels Construction drives sheet pile with an ICE44 crane-suspended vibratory hammer ("vibro hammer"). Sitework for the construction of a 31-story highrise in Milwaukee, Wisconsin. The project is located along the Milwaukee River in the Third Ward neighborhood, at 333 North Water. Hines is the developer, the general contractor is W.E. O'Neil, and Michels is doing the foundation work.

 

September 15, 2022

Original key: IMG_1480

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

 

'Scar' for ramp light.

Truck 424, a newer T800 belonging to Pioneer Sand Company. This one has a Caterpillar C11, 10 speed, and 3.90 rears. It also has an electric tarp, rock tub dump body, and high lift gate. Pioneer's tandems do mostly residential and commercial deliveries of landscape products and materials. Hence, they're geared more for on-road use than for sitework. Also note the lever in the middle of the dump body for the split gate, which allows two separate commodities (or two separate mixtures of commodities) to be carried together without being mixed together. Great for when a single order contains two products, or when two small orders can be shipped together. The split gate can be a pain in the ass, though. There've been a couple times where I'd be loaded with a full load of a single product, and the gate would latch down during the loading process. A lot of the time, I'd have to dump out the back portion, bring the bed down, put the truck in motion, slam on the brakes when I had built up enough speed, get out to pull the gate open, then go back to the pile and dump again. Also, with that gate closed and product in the front compartment, one has to be extremely careful not to allow the truck to tip over.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

 

Ramp lighting being removed in preparation for demolition.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

 

Ramp lighting during removal in preparation for demolition.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

My beautiful picture

 

LOOKING FOR MORE CREATIVE COMMONS PHOTOS?

 

I SHARE A MUCH LARGER CC PHOTO ARCHIVE ON MY OFFICIAL WEBSITE:

 

👉 nenadstojkovicart.com/albums/gallery/3

 

At the top in the middle is an option to search by keyword.

  

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

 

Rooftop ramp being prepared for demolition.

was hoping to catch smooth new paving. don't use.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

 

Bridge to parking lot closed until completion of Aldi.

Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.

Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.

Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.

Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.

 

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

 

Ramp lighting being removed as part of demolition.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

 

Ramp light after removal.

$29 million, multi-phased project within an occupied museum; 23,000 sf new addition onto existing building included ticket booth, lobby, flexible exhibit spaces, covered outdoor seating, Adventure Center, hardscaping, sitework, and landscaping package; 150,000 sf renovation included updating multiple exhibit areas, new finishes, administrative offices, dining facility, installation of elevator, and new green sustainable roof; addition achieved LEED® Gold Certificatio

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

 

Ramp lighting after removal.

Granada Village Shopping Center Redevelopment (Building A1 & A3 Roof Construction - 2012-02-09) - Granada Hills, CA. Urban One www.urbanone.com.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.

Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.

Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.

Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.

 

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Parents, buy your children some plastic toy bulldozers and excavators and cranes etc., then put them in dirt and show them this picture.

 

-----------------------

 

In downtown Toronto on September 24th, 2016, at the northeast corner of Yonge Street and Alexander Street.

 

-----------------------

 

Getty Thesaurus of Geographic Names terms:

• Toronto (7013284)

 

Art & Architecture Thesaurus terms:

• construction equipment (300022242)

• construction sites (300312090)

• excavating equipment (300022294)

• skyscrapers (300004809)

• urban landscapes (300132447)

 

Wikidata items:

• Downtown Toronto (Q2944796)

• September 24 (Q2890)

• September 2016 (Q19249552)

• Yonge Street (Q20725)

Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-09) - Granada Hills, CA. Urban One www.urbanone.com.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

I made a handful of models today for placement in a scene that will go with a bunch of other skyscrapers and roads made by co-workers for a large 3d city space. This is my part, the suburbs.

Granada Village Shopping Center Redevelopment (Phase 2 Dining District Sitework Construction - 2012-03-06) - Granada Hills, CA. Urban One www.urbanone.com.

Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.

Visit us at www.bigiron4sale.com

Granada Village Shopping Center Redevelopment (Phase 2 Dining District Sitework Construction - 2012-01-25) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A3 & A4 Facade Construction - 2012-01-25) - Granada Hills, CA. Urban One www.urbanone.com.

My beautiful picture

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

This CASE 9040 Hydraulic Excavator demolished the old sanctuary building at Mount Moriah Primitive Baptist Church near Uptown Charlotte in January 2011.

1 2 3 4 6 ••• 74 75