uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
on the trailer
the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:
bnstudio.com.au/page/
The project was supported by Bundanon Trust
and produced as part of SiteWorks:
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Newly constructed sitework / drainage and stormwater infrastructure associated with the Hoods Creek Sanitary Sewage Attenuation Basin, an underground sanitary sewage storage facility. Caledonia, Wisconsin, near Racine. September 2013.
assessing
the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:
bnstudio.com.au/page/
The project was supported by Bundanon Trust
and produced as part of SiteWorks:
Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.
Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.
Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.
Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.
Building 1
Wood Framing installation is complete.
Roof Trusses are moving forward at the Northside.
Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.
Shingle and Flat Roof Installation is underway and 35% complete.
Building weather wrap is being installed and 40% complete.
Courtyard waterproofing prep is underway.
Building 2
Wood Framing installation is complete.
Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.
Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 30% complete.
Building 3
Underground Rough is 100% complete
The slab is poured and waiting for wood framing to commence.
Building 4
Foundation is 1000% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 25% complete
Underground Electrical Rough is 50% complete
Building 5
Foundation, underground utilities, and the slab is complete.
Progress pending framing start forecasted to for October 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is underway and 50% complete.
Site curbs are being installed
Sitework
Curb formwork and installation has started on Mill Road
Setting building site to final subgrade
Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete
assesing
the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:
bnstudio.com.au/page/
The project was supported by Bundanon Trust
and produced as part of SiteWorks:
Granada Village Shopping Center Redevelopment (Burger King Sidewalk - 2012-03-06) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A1 - TJ Maxx Facade Construction - 2011-10-06) - Granada Hills, CA. Urban One www.urbanone.com.
Building 1
Wood Framing installation is complete.
Roof Trusses are moving forward at the Northside.
Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.
Shingle and Flat Roof Installation is underway and 35% complete.
Building weather wrap is being installed and 40% complete.
Courtyard waterproofing prep is underway.
Building 2
Wood Framing installation is complete.
Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.
Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 30% complete.
Building 3
Underground Rough is 100% complete
The slab is poured and waiting for wood framing to commence.
Building 4
Foundation is 1000% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 25% complete
Underground Electrical Rough is 50% complete
Building 5
Foundation, underground utilities, and the slab is complete.
Progress pending framing start forecasted to for October 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is underway and 50% complete.
Site curbs are being installed
Sitework
Curb formwork and installation has started on Mill Road
Setting building site to final subgrade
Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete
Building 1
Wood Framing installation is complete.
Roof Trusses are moving forward at the Northside.
Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.
Shingle and Flat Roof Installation is underway and 35% complete.
Building weather wrap is being installed and 40% complete.
Courtyard waterproofing prep is underway.
Building 2
Wood Framing installation is complete.
Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.
Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 30% complete.
Building 3
Underground Rough is 100% complete
The slab is poured and waiting for wood framing to commence.
Building 4
Foundation is 1000% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 25% complete
Underground Electrical Rough is 50% complete
Building 5
Foundation, underground utilities, and the slab is complete.
Progress pending framing start forecasted to for October 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is underway and 50% complete.
Site curbs are being installed
Sitework
Curb formwork and installation has started on Mill Road
Setting building site to final subgrade
Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete
reference plumbline
the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:
bnstudio.com.au/page/
The project was supported by Bundanon Trust
and produced as part of SiteWorks:
Once at the new site, buildings were renovated including new paint, wall coverings, carpet & vinyl flooring. New electrical was run to the buildings and buildings were connected to the school's fire alarm and data systems.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
thinning the brk
the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:
bnstudio.com.au/page/
The project was supported by Bundanon Trust
and produced as part of SiteWorks:
The walls of the Totem Lake/128th St HOV ramp provide a 33,000 square-foot canvas for artist expression.
Granada Village Shopping Center Redevelopment (Building A3 & A4 Facade Construction - 2012-02-29) - Granada Hills, CA. Urban One www.urbanone.com.
Construction at Cahill Park, Whitefish Bay, Wisconsin. September 2013. This photo shows construction of wall, paving, landscaping adjacent to baseball field backstop.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2011-09-22) - Granada Hills, CA. Urban One www.urbanone.com.
peg
the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:
bnstudio.com.au/page/
The project was supported by Bundanon Trust
and produced as part of SiteWorks:
the crew debrief
the building of a bark canoe in Bundanon with Kim Wallis, Steve Russell and Noel Lonesborough from Boolarng Nangamai Aboriginal Corporation:
bnstudio.com.au/page/
The project was supported by Bundanon Trust
and produced as part of SiteWorks:
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.
Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.
Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.
Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.
Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-26) - Granada Hills, CA. Urban One www.urbanone.com.