Building 1
Wood Framing installation is complete.
Roof Trusses are moving forward at the Northside.
Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.
Shingle and Flat Roof Installation is underway and 35% complete.
Building weather wrap is being installed and 40% complete.
Courtyard waterproofing prep is underway.
Building 2
Wood Framing installation is complete.
Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.
Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 30% complete.
Building 3
Underground Rough is 100% complete
The slab is poured and waiting for wood framing to commence.
Building 4
Foundation is 1000% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 25% complete
Underground Electrical Rough is 50% complete
Building 5
Foundation, underground utilities, and the slab is complete.
Progress pending framing start forecasted to for October 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is underway and 50% complete.
Site curbs are being installed
Sitework
Curb formwork and installation has started on Mill Road
Setting building site to final subgrade
Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete
Newly constructed sitework / drainage and stormwater infrastructure associated with the Hoods Creek Sanitary Sewage Attenuation Basin, an underground sanitary sewage storage facility. Caledonia, Wisconsin, near Racine. September 2013.
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.
Visit us at www.bigiron4sale.com
Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.
Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.
Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.
Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.
Granada Village Shopping Center Redevelopment (Exterior Decorative Carriage Lights - 2012-02-20) - Granada Hills, CA. Urban One www.urbanone.com.
One of the few places that doesn't have a trace of this weeks snow storm is the construction site at Brigham and Women's.
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.
Bridge to parking lot closed until Aldi is 100% completed.
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
Construction continues on the site of the Mass General's new B3C building (Building for the Third Century). Here stone from the foundation of the previous building is hauled away.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.
Visit us at www.bigiron4sale.com
Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-01-27) - Granada Hills, CA. Urban One www.urbanone.com.
This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.
This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
Construction continues on the site of the Mass General's new B3C building (Building for the Third Century).
Building 1
Wood Framing installation is complete.
Roof Trusses are moving forward at the Northside.
Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.
Shingle and Flat Roof Installation is underway and 35% complete.
Building weather wrap is being installed and 40% complete.
Courtyard waterproofing prep is underway.
Building 2
Wood Framing installation is complete.
Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.
Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 30% complete.
Building 3
Underground Rough is 100% complete
The slab is poured and waiting for wood framing to commence.
Building 4
Foundation is 1000% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 25% complete
Underground Electrical Rough is 50% complete
Building 5
Foundation, underground utilities, and the slab is complete.
Progress pending framing start forecasted to for October 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is underway and 50% complete.
Site curbs are being installed
Sitework
Curb formwork and installation has started on Mill Road
Setting building site to final subgrade
Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.
Granada Village Shopping Center Redevelopment (Pad L Interior Construction - 2012-02-29) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building B Stein Mart Facade Construction - 2012-01-30) - Granada Hills, CA. Urban One www.urbanone.com.
This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.