View allAll Photos Tagged sitework
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.
Visit us at www.bigiron4sale.com
Granada Village Shopping Center Redevelopment (Exterior Decorative Carriage Lights - 2012-02-20) - Granada Hills, CA. Urban One www.urbanone.com.
One of the few places that doesn't have a trace of this weeks snow storm is the construction site at Brigham and Women's.
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.
Bridge to parking lot closed until Aldi is 100% completed.
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
Construction continues on the site of the Mass General's new B3C building (Building for the Third Century). Here stone from the foundation of the previous building is hauled away.
LOOKING FOR MORE CREATIVE COMMONS PHOTOS?
I SHARE A MUCH LARGER CC PHOTO ARCHIVE ON MY OFFICIAL WEBSITE:
👉 nenadstojkovicart.com/albums/gallery/3
At the top in the middle is an option to search by keyword.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.
Visit us at www.bigiron4sale.com
Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-01-27) - Granada Hills, CA. Urban One www.urbanone.com.
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.
This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.
This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.
Parents, buy your children some plastic toy bulldozers and excavators and cranes etc., then put them in dirt and show them this picture.
-----------------------
In downtown Toronto on September 24th, 2016, at the northeast corner of Yonge Street and Alexander Street.
-----------------------
Getty Thesaurus of Geographic Names terms:
• Toronto (7013284)
Art & Architecture Thesaurus terms:
• construction equipment (300022242)
• construction sites (300312090)
• excavating equipment (300022294)
• skyscrapers (300004809)
• urban landscapes (300132447)
Wikidata items:
• Downtown Toronto (Q2944796)
• September 24 (Q2890)
• September 2016 (Q19249552)
• Yonge Street (Q20725)
Building 1
Wood Framing installation is complete.
Roof Trusses are moving forward at the Northside.
Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.
Shingle and Flat Roof Installation is underway and 35% complete.
Building weather wrap is being installed and 40% complete.
Courtyard waterproofing prep is underway.
Building 2
Wood Framing installation is complete.
Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.
Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 30% complete.
Building 3
Underground Rough is 100% complete
The slab is poured and waiting for wood framing to commence.
Building 4
Foundation is 1000% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 25% complete
Underground Electrical Rough is 50% complete
Building 5
Foundation, underground utilities, and the slab is complete.
Progress pending framing start forecasted to for October 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is underway and 50% complete.
Site curbs are being installed
Sitework
Curb formwork and installation has started on Mill Road
Setting building site to final subgrade
Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "A Letter to Strangers" was performed and installed at the Memorial Chapel Steps. Photos: Jelena Dakovic.
Granada Village Shopping Center Redevelopment (Building B Stein Mart Facade Construction - 2012-01-30) - Granada Hills, CA. Urban One www.urbanone.com.
This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
mcad.edu Four permanent murals designed and produced by students in Elissa Cedarleaf Dahl's Fine Arts Studio Siteworks class will be unveiled at the historic Parkway Theater.
Photograph ©Erin Nicole Johnson for the Minneapolis College of Art and Design