View allAll Photos Tagged sitework

''Twilight States and the Edges of Darkness is a collaborative site-specific mixed and multimedia installation that responds to a selected site at Bundanon, the rural New South Wales estate gifted to the Australian government by the artist Arthur Boyd to support arts practice and promote engagement with the natural and cultural landscape. Exhibited as part of the Bundanon’s annual one day event Siteworks, this work aims to “create a contemplative space for encountering multi-sensorial, and preternatural connections to the environment through the use of endangered flora in New South Wales. Images of these plants are expressed through embroidered textiles, sculptural forms, and micro-electronics. The audience is encouraged to explore the shifting quality of the work from day to night. Twilight States is a gentle intervention in the landscape that reminds us of our connections to the ecosystems to which we belong.''

 

bundanon.com.au/2016-Artworks/twilight-states-and-edges-d...

HALLA HE130LCE Excavator removing demolition debris from residential demo project in Charlotte, North Carolina. Camera used, Olympus 590UZ.

As lead landscape architect, I met with the Owner and the landscape contractor at least once per week to oversee installation and address any site issues. This image shows the fromwork installation for the concrete playground edge and adjacent concrete paving.

Video clip: Michels Construction uses a Manitowoc crane to lift a sheet pile. The sheet pile will be driven along the bank of the Milwaukee River with a crane-suspended vibratory hammer ("vibro hammer"). Sitework for the construction of a 31-story highrise in Milwaukee, Wisconsin. The project is located in the Third Ward neighborhood, at 333 North Water. Hines is the developer, the general contractor is W.E. O'Neil, and Michels is doing the foundation work.

 

September 15, 2022

Original key: IMG_1450

 

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

Site work continues on the Mass General's new Building for the Third Century (B3C). (Taken through a window as the reflections indicate.)

W.C. Black and Sons, Inc. performed total demolition of the old Charlotte Boxing Academy with a CASE 9040 excavator in January of 2011. Photo taken with an Olympus 590UZ.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

Main Street art project: a big wall of slate where people can add their own artwork to this piece of art.

 

The 54-foot Community Chalkboard and Podium monument, located in front of the Charlottesville City Hall and adjacent to the civic amphitheatre in Charlottesville, Virginia, has been honored with two design awards for architectural excellence - a 2009 Silver Medal Rudy Bruner Award for Urban Excellence and a 2009 Inform Honor Award from the Virginia Chapter of the American Institute of Architects’ (AIA). Designed by architect Robert Winstead of SHW Group and landscape architect Pete O’ Shea of Siteworks, LLC, the interactive monument celebrates free expression and was built to honor the First Amendment of the United States Constitution.

 

deere 690 excavator doing sitework on rennovation job

This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

This project creates a unique symbol and expression for the City of Kirkland, capturing the essence of the city’s natural resources.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

Starting to put in the profiles on the building site

VICTORVILLE US PENITENTIARY - Victorville Penitentiary is a Federal Penitentiary. Project consists of general housing facilities, special detention facilities, medical, shop/training facilities, cafeteria and food processing facility, all within a medium and maximum security configuration. This facility is located in the middle of the desert with an airport facility across the street from Con-Air Transportation.

Scope of work included the HVAC mechanical piping and sheetmetal systems, including the underground HVAC sitework and plumbing.

Aberdeen South Harbour Extension Project

Video clip: Michels Construction drives sheet pile with an ICE44 crane-suspended vibratory hammer. Sitework for the construction of a 31-story highrise in Milwaukee, Wisconsin. The project is located along the Milwaukee River in the Third Ward neighborhood, at 333 North Water.

Hines is the developer, the general contractor is W.E. O'Neil, and Michels is doing the foundation work.

 

September 15, 2022

Original key: IMG_1481

Aberdeen South Harbour Extension Project

Kenneth G. Jackson Memorial Estates in Monroe, Louisiana.

This will involve removal of some trees and demolition of the rooftop carpark ramp which was built some time in the late 1990s.

This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

Recently constructed retaining wall. Construction at Cahill Park, Whitefish Bay, Wisconsin. September 2013.

This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.

Visit us at www.bigiron4sale.com

Image taken of QUT Science and Engineering Centre and Community Hub Project late July, 2011.

Aanvoer van stalen korven voor de fundering van het hoofdgebouw. De kraan lost het wapeningstaal terwijl de chauffeur de lading begeleidt. Op de voorgrond ligt materiaal klaar voor verdere verwerking.

-------------

 

🇬🇧 Delivery of steel reinforcement cages for the foundation of the main building. A crane unloads the material while the truck driver guides it into place. In the foreground, construction supplies are ready for further use.

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

QUT Science and Engineering Centre and Community Hub Project - image taken late July, 2011.

Newly constructed sitework / drainage and stormwater infrastructure associated with the Hoods Creek Sanitary Sewage Attenuation Basin, an underground sanitary sewage storage facility. Caledonia, Wisconsin, near Racine. September 2013.

Vehicle Graphics, high quality 3M vinyl graphics

This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Pictures of heavy equipment working at Big Iron's yard in Jacksonville, FL. This is where we dismantle and containerize heavy equipment to ship overseas.

Visit us at www.bigiron4sale.com

Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.

Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.

Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.

Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.

 

Granada Village Shopping Center Redevelopment (Exterior Decorative Carriage Lights - 2012-02-20) - Granada Hills, CA. Urban One www.urbanone.com.

1 2 4 6 7 ••• 79 80