Granada Village Shopping Center Redevelopment (Building A1 Facade Construction - 2011-10-27) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (R-3 Sidewalk Improvements - 2012-02-10) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Granada Village Shopping Center Redevelopment (Pad L Facade Construction - 2012-01-30) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Rite Aid Facade Construction - 2011-09-15) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Space 9 Vanilla Shell Construction - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.
Luke is subbying for Coogee Freight Services. And is at siteworks laydown area, with Western Power materials for stage 2 developement works. Paul, Coogee Freight Services driver, already has his trailer unloaded, by FEL with forks attachment.
DBCEC, Donnybrook Civil Earthworks Contractors, has the contract to lay underground power supply to the new residential blocks. Works include, street lighting.
Granada Village Shopping Center Redevelopment (Building A1 Roof Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building C1 - HomeGoods Facade Construction - 2011-11-03) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2011-10-27) - Granada Hills, CA. Urban One www.urbanone.com.
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.
Granada Village Shopping Center Redevelopment (Phase 1 Sitework Rite Aid Loading Dock Construction - 2011-06-30) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Space 9 Storefront Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.
Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2011-09-22) - Granada Hills, CA. Urban One www.urbanone.com.
SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.
Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-09) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Phase 2 Sitework Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (EV Charging Stations Construction - 2012-01-25) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.