Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 DIning District Sitework Construction - 2012-02-24) - Granada Hills, CA. Urban One www.urbanone.com.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.

Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-01-12) - Granada Hills, CA. Urban One www.urbanone.com.

Colin Philips Contracting - using the digger to flatten out our building platform. Need to dig into the site quite a bit.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.

Granada Village Shopping Center Redevelopment (Building A2 Roof Construction - 2012-01-31) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (NetLINK Lighting Controller Installation - 2012-01-31) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 Dining District Sitework Construction - 2012-01-27) - Granada Hills, CA. Urban One www.urbanone.com.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 DIning District Sitework Construction - 2012-02-09) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A2 Roof Construction - 2012-02-10) - Granada Hills, CA. Urban One www.urbanone.com.

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Granada Village Shopping Center Redevelopment (Building A1 Roof Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.

Digger has finishing it's work - building platform cut into the site and pegged out.

Granada Village Shopping Center Redevelopment (New Pad J Grading - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A1 Roof Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 DIning District Sitework Construction - 2012-02-09) - Granada Hills, CA. Urban One www.urbanone.com.

Plaza Hermosa (Sitework - 2013-04-11) - Hermosa Beach, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-24) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Rite Aid Interior Construction - 2011-08-04) - Granada Hills, CA. Urban One www.urbanone.com.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.

Granada Village Shopping Center Redevelopment (Building A1 TJ Maxx Facade Construction - 2011-11-17) - Granada Hills, CA. Urban One www.urbanone.com.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2011-05-12) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 1 Completion - 2011-09-08) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-02) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building C1 HomeGoods Facade Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 DIning District Sitework Construction - 2012-02-24) - Granada Hills, CA. Urban One www.urbanone.com.