Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2011-09-15) - Granada Hills, CA. Urban One www.urbanone.com.

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

Granada Village Shopping Center Redevelopment (Phase 2 Sitework Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A2 - Pick Up Stix Facade Construction - 2011-10-06) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Rite Aid Interior Construction - 2011-08-04) - Granada Hills, CA. Urban One www.urbanone.com.

Now this was fun. In OH, you're only allowed to burn for a few hours in the afternoon/eve and that wasn't working out with anyone's schedule. So we rented a chipper. What an incredible mess. Shot out one window on the garage, and I got ringworm. End of story.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "move." was performed and installed at the Art-Sociology Building Atrium. Photos: Jelena Djakovic.

Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

Granada Village Shopping Center Redevelopment (Phase 2 Sitework Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A1 Roof Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 Trash Enclosure Construction - 2012-01-25) - Granada Hills, CA. Urban One www.urbanone.com.

Initial sitework begins at Ellis INFINITI of Little Rock

01 AUG 2011

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

SITEWORK STABLE & ARENA

Granada Village Shopping Center Redevelopment (Pad L Facade Construction - 2012-01-27) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 1 Completion - 2011-09-08) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2011-05-12) - Granada Hills, CA. Urban One www.urbanone.com.

the one of the left is a model of south east australia bark canoe from a single bark sheet of the Stringy bark, the ome on the right is a model from the Tasmanian sistem of canoe-making, out of rolled paperbark

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Traffic Circle Construction - 2011-07-07) - Granada Hills, CA. Urban One www.urbanone.com.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

SiteWorks are performances on campus that marked the culmination of a collaboration between Dance and Creative Placemaking Architecture students who have been developing site-specific works over the course of the spring semester. The SiteWork "Burn - The Fire of 1912" was performed and installed at the Point of Failure. Photos: Jelena Dakovic.

preparing a nettle soup at Siteworks

www.bundanon.com.au/category/siteworks/the_lab

 

Image by Alex Kershaw

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Main Entry Drive Construction - 2011-06-23) - Granada Hills, CA. Urban One www.urbanone.com.

1 2 ••• 32 33 35 37 38 ••• 79 80