Granada Village Shopping Center Redevelopment (Petco Interior Construction - 2011-08-04) - Granada Hills, CA. Urban One www.urbanone.com.

Drains dug today for power and communications cables

Granada Village Shopping Center Redevelopment (Phase 2 Sitework Construction - 2011-11-03) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-01-27) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-26) - Granada Hills, CA. Urban One www.urbanone.com.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2011-10-20) - Granada Hills, CA. Urban One www.urbanone.com.

Katalog : Sidney M Levy

Construction Databook

Penerbit McGraw Hill, USA, 1998

 

Deskripsi : Sitework, Site Utilities, Concrete, Masonry, Structural Steel, Joists, and Metal Decks, Wood and Lumber Products, Plywood, Composite Wood Products, High-Pressure Laminates, Roofing, etc.

 

Jumlah : 682 hal. - 32496 KB

 

Unduh : www.mediafire.com/?d27y888558wlw4j

 

Copyright ©pakteguhs.blogspot.com

Granada Village Shopping Center Redevelopment (Pad L Domestic Water Line Installation - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building B Stein Mart Facade Construction - 2012-01-25) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2012-01-25) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Pad L Facade Construction - 2012-02-08) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-24) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A3 & A4 Facade Construction - 2012-01-26) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A1 TJ Maxx Roof Construction - 2012-01-12) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2011-05-12) - Granada Hills, CA. Urban One www.urbanone.com.

1] Siteworks had 4 guys working on front side of canopy grades. 148 yards of undercut was removed.

 

2] Southeastern pump and tank had 9 guys working on fuel lines.

 

3] M&J had 5 guys working on interior rough.

 

4] Doster had 6 guys working on FRP, hanging sheetrock, plywood and finishing.

 

5] Doster had 2 guys working on paint on roof screens.

 

6] CE holt had 3 guys working on setting roof top equipment and interior cooler doors.

 

7] Tino tile had 2 guys working on floor and wall tile.

Granada Village Shopping Center Redevelopment (DWP Water Line Construction - 2012-02-10) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Pylon Sign Construction - 2011-09-22) - Granada Hills, CA. Urban One www.urbanone.com.

Artwork exhibited as part of Siteworks 2010

www.bundanon.com.au/siteworks

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Terminal 4 @ Port Everglades - some wildlife liking the landscape features already

sitework, foundation, framing, siding, windows, and doors.

Man driving a screed machine

Granada Village Shopping Center Redevelopment (Pad L Interior Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A3 & A4 Facade Construction - 2012-01-25) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Rite Aid Interior Construction - 2011-08-04) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 DIning District Sitework Construction - 2012-02-24) - Granada Hills, CA. Urban One www.urbanone.com.

1] Siteworks had 4 guys working on front side of canopy grades. 148 yards of undercut was removed.

 

2] Southeastern pump and tank had 9 guys working on fuel lines.

 

3] M&J had 5 guys working on interior rough.

 

4] Doster had 6 guys working on FRP, hanging sheetrock, plywood and finishing.

 

5] Doster had 2 guys working on paint on roof screens.

 

6] CE holt had 3 guys working on setting roof top equipment and interior cooler doors.

 

7] Tino tile had 2 guys working on floor and wall tile.

Granada Village Shopping Center Redevelopment (Phase 1 Sitework Construction - 2011-05-12) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 Sitework Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.