This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

Lucky find at Target for some limited #Funko Pop figures to add to my collection. #Toothless #OfficeSpace

Cozy, interior office suite available in boutique 36th Street building centrally located off Seventh Avenue in the midst of Manhattan's popular Fashion District/Times Square South neighborhoods. Space features hardwood floors, exposed ceilings, exposed brick walls and is configured with two (2) interior offices and open bullpen for 6-8 workstations. Space measures 1,200 sf and asking rent is $27.00/sf, $2,700/month.

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

New Village is strategically located at the “Four Corners” of the Village. New Village is a 4.87 acre mixed-use, multi-modal, residential redevelopment bounded by Main Street to the south, North Ocean Avenue to the east, Lake Street to the north and a parcel to the west of Havens Avenue. The site, sitting on a total of 3.28 acres of private land, consists of six parcels surrounding by a 1.68 acre Village parking lot. The project includes reshaping the existing Village property boundary while maintaining the overall acreage and parking count.

The entire project includes 291 residential apartment units and 36,149 square feet of restaurant and retail space. Additionally, the project will have a total of 509 parking spaces screened from the street beneath the residential buildings and in surface lots.

During this phase of construction on New Village:

 

- All roofing operations were completed.

- Progression of cementitious siding

- Masonry veneer work at Building #5 was in progress

- Interior drywall operations at Buildings #1 and #2

- Finishes being installed at Building #1

 

For more about this project visit www.tritecrealestate.com

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

Painting on the wall = office is complete

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Spent all of yesterday/last night cleaning and reorganizing my home office. This is what it looked like 2 years ago.Thought I'd take new pics with natural light and a better camera ;)

The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.

My inspiration came from a composition book with a "recycle" theme, some envelopes and some fun pens. I thought this quilt is perfect to keep your letter writing supplies all together and would be great to send to college with your student as a "hint" to write home!

 

There's a spot for the notebook, this will fit a regular spiral bound notebook or a composition book. A spot for your envelopes, a pen, stamps and one extra spot (checkbook sized) for your address labels.

 

Made in Tampa, Fl.

 

Measurements:

Closed - 10" x 13"

Open - 20" x 13"

Pocket is 6" deep

Stacy Edell

This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

With its rich colors and architectural features, the interior construction of 21,500 square feet of office space for the People’s United Bank Long Island Regional Headquarters creates an elegant space. The space also features a fully automated boardroom and conference rooms with audio/visual systems as well as a 1,200 SF data center that is the hub for all bank operations and includes raised flooring, fully redundant HVAC systems, UPS and generator back up for electric and an FM200 Fire Suppression system.

 

The combination of the rich woods and the steel details creates an environment that is both warm and contemporary.

 

Remember what they had on the board in the movie office space. this reminds me of it.

Cuppa dedicated to my chai-loving flickr friends :-)

In downtown Washington's East End, The Tower Companies and The Lenkin Company turned 1050 K Street—a former parking lot near the old DC Convention Center site—into the beginning of a neighborhood renaissance.

 

This 11-story, 136,000 square-foot LEED Gold boutique office building features the latest techniques in sustainable design—triple-scrubbed indoor air, 100renewable power from wind energy, recaptured runoff and ground water, hi-tech thermal floor-to-floor glass windows that maximize natural light, KONE EcoDisk elevator traction system and a rooftop garden.

 

1050 K Street, Washington DC, Architect: Hickok Cole

American Executive Centers provides beautifully designed and fully furnished executive office space in Plymouth Meeting. For more information go to:

 

www.AmericanExecutiveCenters.com

Stephen Root and Gary Cole in person at the AFI

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Stairs, established 2007.

My cube at Lenel

One of our data servers that we are running our VoIP telephony systems through. We've left extra space for data storage and server space rental.

 

www.pbcoffices.com/locations/sanjose.html

Public computer

fast, secure internet

coffee service

comfortable seating in front of large plasma

 

www.youroffice.com/ballantyne

Your business place, your business partner. Training room available in Addison (North Dallas), Texas by the hour, day, week and longer. Corporate Office Centers provides instant, turnkey workplace solutions with flexible terms for your business and budget.

New Village at Patchogue project has almost completed construction of all structures in their vertical rise. Roof trusses are topping off Buildings 3 and 4 to the West while Buildings 2, 1, and 5 are fully roofed. Siding systems at Buildings 2 and 1 are very far along with trim details at Decks being completed. The building elevations present many different features and with much in place, the true charm of the buildings is becoming evident.

 

Exterior site features are being prepared to accommodate parking lot, sidewalk and landscape features and interior features are becoming a primary focus in the move toward completed buildings.

 

Exterior Brick and Stone are commencing at Building 5 while these features are nearing completion already at Buildings 1 and 2.

 

The interior of Building 1 is being trimmed, painted and tiled with cabinetry and floorcovering features moving forward as well. Building 2 is currently being sheetrocked and similar progress is soon to follow at Building 5.

 

These are photos of the C3 Co-Working space at the Cambridge Innovation Center in Cambridge, MA.

Interior Shot of office space available to rent at 22-24 Cumberland Street, Macclesfield

Aerial photographs of the construction of the New Village Development.

 

For more information on this project please visit www.newvillagepatchogue.com

For more information about TRITEC please visit www.tritecrealestate.com

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Located in a prominent position on the Park Road, and opposite the Metrolink station, Nelson House offers easy access across Altrincham, Salford Quays and central Manchester.

 

Magnus are pleased to announce that there is just one office of 1152 sq ft (10 – 15 person office) currently left at Nelson House

1 2 ••• 29 30 32 34 35 ••• 79 80