View allAll Photos Tagged Telehandler

My Lego telehandler is loosely based on CAT TL642. Buwizz and iPad are used to control it remotely. There are four motorized functions: drive with PF L motor, boom elevation with PF L motor, fork tilt with M motor, and steering with PF servo. Front wheels are driven through a differential, and the rear axle has a simple suspension. Overall, it is maneuverable, easy to control thanks to the proportional control of Buwizz, and very fun to play with. Please watch the video for a demonstration. When sharing, please include the link to my instagram www.instagram.com/legomarat/

Drivers eye view of full reach

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

EA Project Logistics recently completed a complex and potentially difficult project in Bangkok. The project involved the un-stuffing of 60 containers each holding two waste compactor units which were to be stored at a designated lay down area.

The units had arrived from Shanghai China and were to be used by the BMA (Bangkok Metropolitan Administration).

 

CEA carried out methodology studies and ascertained that the project would require two teams of 6 working 24 hours to meet the three day deadline. As Bangkok has transit restrictions for the transport of containers from 10am – 3pm and with the continuing demonstrations, timing and efficiency were key to a successful execution.

 

The day shift team arrived early in the afternoon to begin mobilization, the first convoy of containers arrived soon after and assembled in the parking area.

 

The first container was moved into position and opened, a CEA Manitou Telehandler placed its forks under the first compactor and slowly reversed until 2/3rds of the compactor were exposed. A CEA 14 ton forklift then positioned itself at the side of the compactor and raised its forks to take the weight, the Telehandler and container truck then withdrew from the area allowing the forklift to transport the compactor across the yard to the designated laydown area.

 

The night shift team arrived at 6pm and continued the process throughout the night, as the hours passed by, the teams increased their efficiency resulting in completion of the project in 2.5 days much to the delight of the client.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Lowering Mid Shield 8 December 2012 - JCB Telehandler (most versatile machine)

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

A CAT telehandler was on hand in all ports to position gangways so we could enjoy our days on each island.

Premier étage pour les bureaux - first floor for offices

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

EA Project Logistics recently completed a complex and potentially difficult project in Bangkok. The project involved the un-stuffing of 60 containers each holding two waste compactor units which were to be stored at a designated lay down area.

The units had arrived from Shanghai China and were to be used by the BMA (Bangkok Metropolitan Administration).

 

CEA carried out methodology studies and ascertained that the project would require two teams of 6 working 24 hours to meet the three day deadline. As Bangkok has transit restrictions for the transport of containers from 10am – 3pm and with the continuing demonstrations, timing and efficiency were key to a successful execution.

 

The day shift team arrived early in the afternoon to begin mobilization, the first convoy of containers arrived soon after and assembled in the parking area.

 

The first container was moved into position and opened, a CEA Manitou Telehandler placed its forks under the first compactor and slowly reversed until 2/3rds of the compactor were exposed. A CEA 14 ton forklift then positioned itself at the side of the compactor and raised its forks to take the weight, the Telehandler and container truck then withdrew from the area allowing the forklift to transport the compactor across the yard to the designated laydown area.

 

The night shift team arrived at 6pm and continued the process throughout the night, as the hours passed by, the teams increased their efficiency resulting in completion of the project in 2.5 days much to the delight of the client.

Machine at full reach of 9.2 metres

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

1 2 ••• 28 29 31 33 34 ••• 79 80