This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
New Village Aerials 3/1914
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.