New Village Aerials 3/1914

This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 