This aerial photograph represents construction progress for the New Village project, a 291 unit mixed-use development, as of December 14, of 2012. The phase of the project includes the site and concrete foundation development progressing at Buildings 3, 5, and 1 which are the Westerly most and Easterly most portions of the structure. Structural mat slabs, ramps and perimeter foundation walls are progressing at the Building's 5 and 1 located along the East side of the site. The entire mat slab and perimeter foundation is complete at Building 3 along the West side of the site and the post tension elevated slab is 80 % complete at the same Building. The sub grade structure is being excavated for Building 2 (at center of site) and the subsurface waterproofing membrane is being installed at spread footing locations. Additional scope that is progressing at this time includes the Mechanical, Electrical and Plumbing scope that is being installed within and below slabs.
New Village at Patchogue project has almost completed construction of all structures in their vertical rise. Roof trusses are topping off Buildings 3 and 4 to the West while Buildings 2, 1, and 5 are fully roofed. Siding systems at Buildings 2 and 1 are very far along with trim details at Decks being completed. The building elevations present many different features and with much in place, the true charm of the buildings is becoming evident.
Exterior site features are being prepared to accommodate parking lot, sidewalk and landscape features and interior features are becoming a primary focus in the move toward completed buildings.
Exterior Brick and Stone are commencing at Building 5 while these features are nearing completion already at Buildings 1 and 2.
The interior of Building 1 is being trimmed, painted and tiled with cabinetry and floorcovering features moving forward as well. Building 2 is currently being sheetrocked and similar progress is soon to follow at Building 5.
Used to be the local flagship store of Eaton's, then it passed into Sears' hands. Now, it stands empty, awaiting a new anchor tenant.
Target?
Nordstrom?
Someone else?
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
Amanda McAllister (ChangeUp), Scott Fournier (Discount Tire), Jessica Itchue (Citizens Bank) Nick Waeltz (Green Thumb Industries)
The New Village at Patchogue project has progressed nicely beyond 90% of all subgrade structural features and about 60% of the elevated structural post-tension slab work is completed or in progress. Building 1 spearheads the vertical rise with two levels currently framed and Masonry construction rising above the wood framing. Building 2 will under way with its first floor of wood framing by the end of April 2013. Mechanical, Electrical and Plumbing trades have been coordinating with ongoing structural components in all buildings as the system installation needs progress, and installation of roughed out systems in sub grade and framed units is well under way.
External site improvements are partially placed while the installation of a major portion of subgrade sewer, power, communication and drainage systems that will serve the project are scheduled to commence shortly. By the end of May, the last section of connecting structural slab is expected at the crossover to Havens Avenue opposite Jennings and will complete the footprint for vertical construction at buildings 1, 2, 3 and 5. Building 4 is scheduled to start excavation at West side of the site (on Main Street) to make way for the foundation at the last structure in the project.