View allAll Photos Tagged officespaces
During this phase of construction on New Village:
- All roofing operations were completed.
- Progression of cementitious siding
- Masonry veneer work at Building #5 was in progress
- Interior drywall operations at Buildings #1 and #2
- Finishes being installed at Building #1
For more about this project visit www.tritecrealestate.com
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.
External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.
The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.
Nice Office Suite for Rent; split level; two private offices, reception area, vaulted ceiling, private restroom, private decks for each office, nice wooded location, call (360) 556-7703 for inquiries to sublet or assume lease.
During this phase of construction on New Village:
- All roofing operations were completed.
- Progression of cementitious siding
- Masonry veneer work at Building #5 was in progress
- Interior drywall operations at Buildings #1 and #2
- Finishes being installed at Building #1
For more about this project visit www.tritecrealestate.com
Centennial - Natomas Building 4, Photo 3
Freeport West's commercial properties are conveniently located near major freeways so as to better serve our customers' needs.
Location:
4380 West 1900 South
Salt Lake City, Utah
Classification:
Warehousing / Shipping
Divisible Size (sq.ft.):
10,000
Max. Contiguous Space Available (sq.ft.):
81,118
Min. Divisible Space (sq.ft.):
10,000
Office Area (sq.ft.):
3,478
Building Size (sq.ft.):
81,118
Total Area Available (sq.ft.):
10,000
Click for more information about Centennial - Natomas Building 4's industrial properties warehouse.
Freeport West has been developing, leasing and managing commercial industrial space and warehouse distribution centers since 1963. Our diverse inventory includes properties that can be used for industrial, manufacturing, distribution, shipping, warehouse distribution centers, storage (dry space, refrigerated space or cold storage), showroom, office, flex space and even food grade facilities. We are also Certified Commercial Investment Members (CCIM) of the CCIM Institute.
The New Village at Patchogue project has progressed nicely beyond 90% of all subgrade structural features and about 60% of the elevated structural post-tension slab work is completed or in progress. Building 1 spearheads the vertical rise with two levels currently framed and Masonry construction rising above the wood framing. Building 2 will under way with its first floor of wood framing by the end of April 2013. Mechanical, Electrical and Plumbing trades have been coordinating with ongoing structural components in all buildings as the system installation needs progress, and installation of roughed out systems in sub grade and framed units is well under way.
External site improvements are partially placed while the installation of a major portion of subgrade sewer, power, communication and drainage systems that will serve the project are scheduled to commence shortly. By the end of May, the last section of connecting structural slab is expected at the crossover to Havens Avenue opposite Jennings and will complete the footprint for vertical construction at buildings 1, 2, 3 and 5. Building 4 is scheduled to start excavation at West side of the site (on Main Street) to make way for the foundation at the last structure in the project.
Yeah our desk is huge and the room is not so much.
We pulled out the white (ugh) wall-to-wall carpeting, sanded and stained the original pumpkin pine floors (swoon), knocked down the wall that was enclosing the chimney, painted the walls a happy shade of pear green (Spring Dust by Benjamin Moore)
The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.
TRITEC acquired 135 Engineers Road, a 65,000 square foot industrial building and converted it to 55,000 sf of office space in the in the Hauppauge Industrial Park. This photograph features the Avnet Suite and was taken by Steve Geraci of Reflex Photo.
The building was developed constructed and is currently managed by TRITEC a limited amount of space is still available.
TRITEC acquired 135 Engineers Road, a 65,000 square foot industrial building and converted it to 55,000 sf of office space in the in the Hauppauge Industrial Park. This photograph features the Avnet Suite and was taken by Steve Geraci of Reflex Photo.
The building was developed constructed and is currently managed by TRITEC a limited amount of space is still available.
The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.
External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.
Business networking becomes organic at virtual office centers. Many of our Cloud Virtual Offices have integrated business lounges where you can catch up on stocks on the plasma tv, enjoy a fresh cup of coffee, and chat with other suite residents.
My team captain in front of me with mostly empty beer bottles.
(I admit this picture was staged and the beers were in fact drunk the other afternoon during a government-sanctioned event)
New Village at Patchogue project has almost completed construction of all structures in their vertical rise. Roof trusses are topping off Buildings 3 and 4 to the West while Buildings 2, 1, and 5 are fully roofed. Siding systems at Buildings 2 and 1 are very far along with trim details at Decks being completed. The building elevations present many different features and with much in place, the true charm of the buildings is becoming evident.
Exterior site features are being prepared to accommodate parking lot, sidewalk and landscape features and interior features are becoming a primary focus in the move toward completed buildings.
Exterior Brick and Stone are commencing at Building 5 while these features are nearing completion already at Buildings 1 and 2.
The interior of Building 1 is being trimmed, painted and tiled with cabinetry and floorcovering features moving forward as well. Building 2 is currently being sheetrocked and similar progress is soon to follow at Building 5.
D&S Advertising, Inc. is an established marketing and advertising firm. They provide a Cost Effective way to reach a target audience without sacrificing Distribution, Products, & Services. Their suite is located on the second floor of 31 West Main Street in Patchogue NY. 31 West Main Street is situated in the heart of a suburban downtown revitalization, the 31 West Building has stood in the Village for close to a century. The building has been completely renovated but still features much of the original masonry to help maintain its 100+ year old character. The building has become the jewel of Main St and is at a prime location in the heart of TRITEC’s New Village project.
31 West Main Street has been developed, renovated and is managed by TRITEC.
Your business place, your business partner. Offices, training and conference rooms by the hour, day, week and longer. Corporate Office Centers provides instant, turnkey workplace solutions with flexible terms for your business and budget. Boca Raton, FL - Royal Palm
Shared office space with a engineer consultant firm on the 4th floor of a 5th Ave building, between 35th and 36th Street, close proximity to Herald Square and Penn Plaza, in the Gramercy neighborhood. Space features hardwood floors, exposed ceilings, views in the front and rear of space with eastern and western exposure, and the rear portion of the office is up for sublease, configured with an open area, perimeter windowed office, 1 interior office, and with shared entrance, wet pantry, and restroom. Space available measures 1,300 sf, and asking rent is $40.00/sf, $4,333.33/month.
Before the big collapse there were many big projects going on in Iceland. One of it was this skyscraper which now stands empty near downtown Reykjavik. There are lot of new building like this around Reykjavik, empty or half finished. Anyone in need of office space?
Reykjavik, Iceland. June 2009.
In downtown Washington's East End, The Tower Companies and The Lenkin Company turned 1050 K Street—a former parking lot near the old DC Convention Center site—into the beginning of a neighborhood renaissance.
This 11-story, 136,000 square-foot LEED Gold boutique office building features the latest techniques in sustainable design—triple-scrubbed indoor air, 100renewable power from wind energy, recaptured runoff and ground water, hi-tech thermal floor-to-floor glass windows that maximize natural light, KONE EcoDisk elevator traction system and a rooftop garden.
1050 K Street, Washington DC, Architect: Hickok Cole
During this phase of construction on New Village:
- All roofing operations were completed.
- Progression of cementitious siding
- Masonry veneer work at Building #5 was in progress
- Interior drywall operations at Buildings #1 and #2
- Finishes being installed at Building #1
For more about this project visit www.tritecrealestate.com