New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

The conversion also gives overnight guests place to stay that isn't the floor or the couch. It also gives me a place to sleep through endless conference calls.

 

Mostly the benefit here is so I don't have to step over my brother's shit spread all over the living room when he comes to visit. He actually has five pairs of shoes in the closet. FIVE.

With its rich colors and architectural features, the interior construction of 21,500 square feet of office space for the People’s United Bank Long Island Regional Headquarters creates an elegant space. The space also features a fully automated boardroom and conference rooms with audio/visual systems as well as a 1,200 SF data center that is the hub for all bank operations and includes raised flooring, fully redundant HVAC systems, UPS and generator back up for electric and an FM200 Fire Suppression system.

 

The combination of the rich woods and the steel details creates an environment that is both warm and contemporary.

 

Remember what they had on the board in the movie office space. this reminds me of it.

West Valley Building #2, Photo 1

 

Freeport West serves the West Valley City area in all of its commercial property needs including warehousing, shipping, and office spaces.

 

Location:

2475 S 3200 W

West Valley City, Utah

 

Classification:

Warehousing / Shipping

 

Divisible Size (sq.ft.):

44,507

Max. Contiguous Space Available (sq.ft.):

367,874

 

Min. Divisible Space (sq.ft.):

44,507

 

Office Area (sq.ft.):

10,658

 

Click for more information about West Valley Building #2's warehouse space in Utah.

 

Freeport West has been developing, leasing and managing commercial industrial space and warehouse distribution centers since 1963. Our diverse inventory includes properties that can be used for industrial, manufacturing, distribution, shipping, warehouse distribution centers, storage (dry space, refrigerated space or cold storage), showroom, office, flex space and even food grade facilities. We are also Certified Commercial Investment Members (CCIM) of the CCIM Institute.

Cuppa dedicated to my chai-loving flickr friends :-)

American Executive Centers provides beautifully designed and fully furnished executive office space in Plymouth Meeting. For more information go to:

 

www.AmericanExecutiveCenters.com

Stephen Root and Gary Cole in person at the AFI

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Hahaha

It's nice to know my coworkers haven't been completely beaten down.

TRITEC acquired 135 Engineers Road, a 65,000 square foot industrial building and converted it to 55,000 sf of office space in the in the Hauppauge Industrial Park. This photograph features the Stantec Suite and was taken by Steve Geraci of Reflex Photo.

 

The building was developed constructed and is currently managed by TRITEC a limited amount of space is still available.

Yeah our desk is huge and the room is not so much.

 

We pulled out the white (ugh) wall-to-wall carpeting, sanded and stained the original pumpkin pine floors (swoon), knocked down the wall that was enclosing the chimney, painted the walls a happy shade of pear green (Spring Dust by Benjamin Moore)

Stairs, established 2007.

Public computer

fast, secure internet

coffee service

comfortable seating in front of large plasma

 

www.youroffice.com/ballantyne

Your business place, your business partner. Training room available in Addison (North Dallas), Texas by the hour, day, week and longer. Corporate Office Centers provides instant, turnkey workplace solutions with flexible terms for your business and budget.

New Village at Patchogue project has almost completed construction of all structures in their vertical rise. Roof trusses are topping off Buildings 3 and 4 to the West while Buildings 2, 1, and 5 are fully roofed. Siding systems at Buildings 2 and 1 are very far along with trim details at Decks being completed. The building elevations present many different features and with much in place, the true charm of the buildings is becoming evident.

 

Exterior site features are being prepared to accommodate parking lot, sidewalk and landscape features and interior features are becoming a primary focus in the move toward completed buildings.

 

Exterior Brick and Stone are commencing at Building 5 while these features are nearing completion already at Buildings 1 and 2.

 

The interior of Building 1 is being trimmed, painted and tiled with cabinetry and floorcovering features moving forward as well. Building 2 is currently being sheetrocked and similar progress is soon to follow at Building 5.

 

These are photos of the C3 Co-Working space at the Cambridge Innovation Center in Cambridge, MA.

Interior Shot of office space available to rent at 22-24 Cumberland Street, Macclesfield

One of the offices used by virtual office clients and home based businesses when they need to get out of the house to meet with a client or just to get some work done. We've set it up so that it looks like it is their regular office so clients never know they work at home in sweat-pants.

 

www.pbcoffices.com/locations/sanjose.html

 

Aerial photographs of the construction of the New Village Development.

 

For more information on this project please visit www.newvillagepatchogue.com

For more information about TRITEC please visit www.tritecrealestate.com

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Located in a prominent position on the Park Road, and opposite the Metrolink station, Nelson House offers easy access across Altrincham, Salford Quays and central Manchester.

 

Magnus are pleased to announce that there is just one office of 1152 sq ft (10 – 15 person office) currently left at Nelson House

Aurora Corporate Center is located just minutes from the 4-way interchange at I-88 and Farnsworth near the Chicago Premium Outlet Mall.

 

Units have 20' ceiling height for optional 2nd story office, mezzanine or storage. The units include 200 amp 3-phase electric, pre-cast concrete construction, access to full covered truck dock and are fully sprinklered. Units 120-122 are for office users and units 105-107 would work for warehouse/production users with drive in doors and access to a truck dock. The campus-style business park is home to a diverse group of businesses and is surrounded by a wildlife sanctuary.

 

View All Commercial Properties for sale in Naperville and Aurora, IL

“And if, if they take my stapler, I will, I will set this building on fire.”

Office space is a commodity at the Huntley Library. Many staff members share desks, phone and computers. Even with a renovation in late 2006, the crowding continues to be an issue.

During this phase of construction on New Village:

 

- All roofing operations were completed.

- Progression of cementitious siding

- Masonry veneer work at Building #5 was in progress

- Interior drywall operations at Buildings #1 and #2

- Finishes being installed at Building #1

 

For more about this project visit www.tritecrealestate.com

I'm the devil, or I'm wearing a scary hockey mask from Kingdom of Loathing that has horns. The Office Space reference is nice.

These are photos of the C3 Co-Working space at the Cambridge Innovation Center in Cambridge, MA.

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

The latest craze.

In addition go providing a drop in space for virtual office space users; one of the big things with our office is to create a sense of community for both virtual office clients, home based businesses and in house office space clients. The benefits of networking and mutual support between clients is really amazing. Beyond even just the networking is that many home based businesses miss out on the interactions of a traditional office, so having a central place to network really can give the best of both worlds.

 

www.pbcoffices.com/locations/sanjose.html

Located in a prominent position on the Park Road, and opposite the Metrolink station, Nelson House offers easy access across Altrincham, Salford Quays and central Manchester.

 

Magnus are pleased to announce that there is just one office of 1152 sq ft (10 – 15 person office) currently left at Nelson House

The New Village at Patchogue project has progressed nicely beyond 90% of all subgrade structural features and about 60% of the elevated structural post-tension slab work is completed or in progress. Building 1 spearheads the vertical rise with two levels currently framed and Masonry construction rising above the wood framing. Building 2 will under way with its first floor of wood framing by the end of April 2013. Mechanical, Electrical and Plumbing trades have been coordinating with ongoing structural components in all buildings as the system installation needs progress, and installation of roughed out systems in sub grade and framed units is well under way.

 

External site improvements are partially placed while the installation of a major portion of subgrade sewer, power, communication and drainage systems that will serve the project are scheduled to commence shortly. By the end of May, the last section of connecting structural slab is expected at the crossover to Havens Avenue opposite Jennings and will complete the footprint for vertical construction at buildings 1, 2, 3 and 5. Building 4 is scheduled to start excavation at West side of the site (on Main Street) to make way for the foundation at the last structure in the project.

 

Rockefeller Group Business Centers is located at 560 S. Winchester Boulevard, in the heart of San Jose. Conveniently located adjacent to Santana Row and the freeways, our serviced office space is the perfect solution to all of your office needs.

 

Contact:

Joanne Escobar

560 S. Winchester Blvd.

San Jose, CA. 95128

joanne@rgbc.com

408.572.5600

www.rgbc.com/san-jose/office-space/

 

#rgbcWORKSPACES

#GetTheBestAddress

The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.

1 2 ••• 29 30 32 34 35 ••• 79 80