View allAll Photos Tagged officespace

Howard Hughes Center - Where Creativity Meets Amenity!

 

Front / side of office building - exterior

In downtown Washington's East End, The Tower Companies and The Lenkin Company turned 1050 K Street—a former parking lot near the old DC Convention Center site—into the beginning of a neighborhood renaissance.

 

This 11-story, 136,000 square-foot LEED Gold boutique office building features the latest techniques in sustainable design—triple-scrubbed indoor air, 100renewable power from wind energy, recaptured runoff and ground water, hi-tech thermal floor-to-floor glass windows that maximize natural light, KONE EcoDisk elevator traction system and a rooftop garden.

 

1050 K Street, Washington DC, Architect: Hickok Cole

During this phase of construction on New Village:

 

- All roofing operations were completed.

- Progression of cementitious siding

- Masonry veneer work at Building #5 was in progress

- Interior drywall operations at Buildings #1 and #2

- Finishes being installed at Building #1

 

For more about this project visit www.tritecrealestate.com

Photo by Matt Koroulis,

Camera: Pentax Zoom 90WR,

Film: Kodak Tmax 400 Black & White 35mm,

Developed and scanned at Panda Lab in Seattle.

*scratches head*

Photos from our Ribbon Cutting Ceremony to celebrate the opening of the One Loudoun Welcome Center!

 

Visit us online, on Facebook or www.oneloudoun.com/

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Nice Office Suite for Rent; split level; two private offices, reception area, vaulted ceiling, private restroom, private decks for each office, nice wooded location, call (360) 556-7703 for inquiries to sublet or assume lease.

TRITEC acquired 135 Engineers Road, a 65,000 square foot industrial building and converted it to 55,000 sf of office space in the in the Hauppauge Industrial Park. This photograph features the Stantec Suite and was taken by Steve Geraci of Reflex Photo.

 

The building was developed constructed and is currently managed by TRITEC a limited amount of space is still available.

Before the big collapse there were many big projects going on in Iceland. One of it was this skyscraper which now stands empty near downtown Reykjavik. There are lot of new building like this around Reykjavik, empty or half finished. Anyone in need of office space?

 

Reykjavik, Iceland. June 2009.

Wearing Mady's hat in the pirate ship.

view of 30 St Mary Axe with Abbey office space on 15th, 28th and 29th floors

Office Space avitar

Photo by Matt Koroulis,

Camera: Pentax Zoom 90WR,

Film: Kodak Tmax 400 Black & White 35mm,

Developed and scanned at Panda Lab in Seattle.

Aerial photographs of the construction of the New Village Development.

 

For more information on this project please visit www.newvillagepatchogue.com

For more information about TRITEC please visit www.tritecrealestate.com

Photos of the larger office (available for rent as of December 1st, 2010) at The Network Hub, 422 Richards Street, Third Floor, downtown Vancouver.

It is bring your cat(s) to work day. They are not pleased.

3CDC has outgrown their current office space and will be moving into this building at the northwest corner of 12th and Walnut. This photo is a handheld HDR that actually turned out fairly decent.

Aerial photographs of the construction of the New Village Development.

 

For more information on this project please visit www.newvillagepatchogue.com

For more information about TRITEC please visit www.tritecrealestate.com

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

... where work gets done ...

The New Village at Patchogue project has progressed nicely beyond 90% of all subgrade structural features and about 60% of the elevated structural post-tension slab work is completed or in progress. Building 1 spearheads the vertical rise with two levels currently framed and Masonry construction rising above the wood framing. Building 2 will under way with its first floor of wood framing by the end of April 2013. Mechanical, Electrical and Plumbing trades have been coordinating with ongoing structural components in all buildings as the system installation needs progress, and installation of roughed out systems in sub grade and framed units is well under way.

 

External site improvements are partially placed while the installation of a major portion of subgrade sewer, power, communication and drainage systems that will serve the project are scheduled to commence shortly. By the end of May, the last section of connecting structural slab is expected at the crossover to Havens Avenue opposite Jennings and will complete the footprint for vertical construction at buildings 1, 2, 3 and 5. Building 4 is scheduled to start excavation at West side of the site (on Main Street) to make way for the foundation at the last structure in the project.

 

After the soulless Initech burns down, Peter gets a job with his neighbor, shoveling up its ruins. Their response? "F***ing ay!"

TRITEC acquired 135 Engineers Road, a 65,000 square foot industrial building and converted it to 55,000 sf of office space in the in the Hauppauge Industrial Park. This photograph features the Stantec Suite and was taken by Steve Geraci of Reflex Photo.

 

The building was developed constructed and is currently managed by TRITEC a limited amount of space is still available.

The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.

The New Village at Patchogue project has emerged into the spring with accomplished milestones that include the completion of the Building 5 elevated structural post-tension slab and the breaking of ground for foundation at Building 4. These two structures will begin the vertical rise along Main Street and will place all of the five buildings in active progress. Building 1 is the Northeast building at the corner of Lake and No. Ocean and is topping out it framed units at the third floor. Building 2 has erected its initial section of the first floor and masonry structures have been completed as some of the stair and elevator shafts. Concrete systems are progressing toward completion of the main structural post-tension slab at the Building 2 & 3 connection and wood systems will follow along that same path. Mechanical, Electrical and Plumbing systems are roughing at framed units.

 

External site work will move toward the installation of sub grade structures and utility distribution conduits to make way for the services that support the project.

 

I believe you have my stapler

1 2 ••• 33 34 36 38 39 ••• 79 80