This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

Going up the road when the corner of my eye snags two yellow crescents. (Ouch.) Pull over, back up, shoot, move on.

Sanctuary Newsong Church

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Nice Office Suite for Rent; split level; two private offices, reception area, vaulted ceiling, private restroom, private decks for each office, nice wooded location, call (360) 556-7703 for inquiries to sublet or assume lease.

Yeah, I know this scenario all too well, those first moments back in the office with a cast or boot and crutches or scooter or some walking aid.

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

Ah the life of international travel... not exactly glamorous is it. Not 4 months ago i was lamenting my assimilation to the backpacker way of life... now with the addition of a Dilbert cartoon to my office space i have been truly re-integrated into the day to day workings of an office bitch...the primary reason for me leaving England in the first place. Oh how i'd like to be sat round a hostel table drinking Chateau Cardboard with a bunch of backpackers now! How fickle i can be.

 

But that picture of a monkey on a goat on a tightrope...ah, makes me feel so much better.

  

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

I believe this stands for Dominion Cotton Mills Company (see here for information about the founder); previously, at this site, had been the Kingston Cotton Manufacturing Company.

 

Kingston, Ontario.

Desk area. Will eventually paint that tired desk white.

Engineers are funny people

www.searchofficespace.com/usa/office-space/avenue-of-the-...

 

Rent Office Space in Avenue of the Americas. Search Office Space helps businesses with office rental and offers cheapest and most flexible for offices to rent. Serviced Offices and Executive Suites with Search Office Space.

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

Residents of Galveston Island are presented with a lifestyle that most people dream about, but are rarely lucky enough to experience in their lifetime.

 

With the perfect blend of vibrant energy and quaint charm, downtown Galveston is an ideal setting for those looking to live or work in a historic district that’s accessible, walk-able, and part of history

 

On any given weekend, it's not unusual to see live musical performances in the park, food and wine tastings, nature exhibits or evening ghost tours along the city streets, but it's the true beauty of the Victorian architecture that has been impeccably preserved by Mitchell Historic Properties that gives this area the unique character and ambiance it has become known for today.

 

Recognized for their quality workmanship and the stellar appearance of their buildings, Mitchell Historic Properties has proudly owned and operated commercial and residential properties in downtown Galveston for over 30 years, including one fourth of the buildings in The Strand National Historic Landmark District and Pier 21 along Galveston’s historic harbor.

 

From retail spaces that date as far back as the 1850's, to apartments or lofts with architectural detail that can only be found in historic buildings, Mitchell Historic Properties has what you need.

 

New Village is strategically located at the “Four Corners” of the Village. New Village is a 4.87 acre mixed-use, multi-modal, residential redevelopment bounded by Main Street to the south, North Ocean Avenue to the east, Lake Street to the north and a parcel to the west of Havens Avenue. The site, sitting on a total of 3.28 acres of private land, consists of six parcels surrounding by a 1.68 acre Village parking lot. The project includes reshaping the existing Village property boundary while maintaining the overall acreage and parking count.

The entire project includes 291 residential apartment units and 36,149 square feet of restaurant and retail space. Additionally, the project will have a total of 509 parking spaces screened from the street beneath the residential buildings and in surface lots.

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.

Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.

 

Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.

 

Public computer

fast, secure internet

telephone for local or inhouse calls

listing of area shops, and resturants

beverage service including starbucks coffee, pepsi, and coke products, and filtered water

microwave

comfortable seating in front of small plasma

www.youroffice.com/ballantyne

Welcome to my office.

New Village is strategically located at the “Four Corners” of the Village. New Village is a 4.87 acre mixed-use, multi-modal, residential redevelopment bounded by Main Street to the south, North Ocean Avenue to the east, Lake Street to the north and a parcel to the west of Havens Avenue. The site, sitting on a total of 3.28 acres of private land, consists of six parcels surrounding by a 1.68 acre Village parking lot. The project includes reshaping the existing Village property boundary while maintaining the overall acreage and parking count.

The entire project includes 291 residential apartment units and 36,149 square feet of restaurant and retail space. Additionally, the project will have a total of 509 parking spaces screened from the street beneath the residential buildings and in surface lots.

*scratches head*

Another shot of my red Swingline stapler.

www.searchofficespace.com/usa/office-space/7th-avenue-exe...

 

Office Space for rent, Executive Suites to Rent and Serviced Offices - these are the main operation fields of Search Office Space in 7th Avenue, New York.

1 2 ••• 22 23 25 27 28 ••• 79 80