Music helps with early literacy! We moved to the music, listen to books with a beat, and Lad lots of fun !
Learners washing hands at Zamani Crèche, which is conditionally registered and awaiting a new PCR certificate for full registration.
As part of SEIS the centre received an additional classroom, a toilet facility, fencing, fire extinguisher installed, waste pit, fixed leaks in the roof, signage.
Child on swing.
Mawozini Crèche is in phase 2 repairs.
Proposed work at the centre includes:
- Additional classroom - the existing facility caters for 46 children, the attendance is just more than the number of children catered for in the existing facility;
- Repairs: the existing is in a relatively good condition, a door needs replacement, 4 locksets need replacing, a number of window panes need replacing, the apron requires repair.
- Fencing - the facility is fenced, however, the area is insufficient, particularly if an additional classroom is required. It is proposed that the area is extended and that the fence is repaired where required.
- Health & Safety: The centre also requires a fire extinguisher, first aid box, safety signage, and a fenced waste pit.
- Toilet facility: The centre has 2 toilet facilities which are both in a relatively poor condition. It is proposed that the face brick facility is repaired and used as a teacher’s toilet, and a new small facility built for the learners, with a new disabled unit included.
- A gutter downpipe is required.
- Play equipment: The facility has play equipment. Some of this equipment is in need of repair. A new shade cloth covering for the play area is required.
- Estimate costs for repairs: R 334 570
Child eating porridge.
Mawozini Crèche is in phase 2 repairs.
Proposed work at the centre includes:
- Additional classroom - the existing facility caters for 46 children, the attendance is just more than the number of children catered for in the existing facility;
- Repairs: the existing is in a relatively good condition, a door needs replacement, 4 locksets need replacing, a number of window panes need replacing, the apron requires repair.
- Fencing - the facility is fenced, however, the area is insufficient, particularly if an additional classroom is required. It is proposed that the area is extended and that the fence is repaired where required.
- Health & Safety: The centre also requires a fire extinguisher, first aid box, safety signage, and a fenced waste pit.
- Toilet facility: The centre has 2 toilet facilities which are both in a relatively poor condition. It is proposed that the face brick facility is repaired and used as a teacher’s toilet, and a new small facility built for the learners, with a new disabled unit included.
- A gutter downpipe is required.
- Play equipment: The facility has play equipment. Some of this equipment is in need of repair. A new shade cloth covering for the play area is required.
- Estimate costs for repairs: R 334 570
Learner on playground at Kopanang Crèche.
Kopanang Crèche is currently conditionally registered and awaiting a new PCR certificate for full registration.
The centre will be receiving a new two-classroom unit, kitchen, pantry, toilet facilities, jungle gym, fencing and signage.
A vibrant baby telescope toy featuring buttons and bright colors sits among other educational toys in a retail display, promoting early learning and sensory development for infants.
During the numeracy class, kids flexed their wrists tracing big and small number five. This is a good exercise for developing their fine motor skills.
whitefieldspreschools.com/2017/01/22/chugga-chugga-choo-c...
Learners on playground at Zamani Crèche, which is conditionally registered and awaiting a new PCR certificate for full registration.
As part of SEIS the centre received an additional classroom, a toilet facility, fencing, fire extinguisher installed, waste pit, fixed leaks in the roof, signage.
In picture: practitioner, Miss Nonhlanhla Ntshangase.
During the numeracy class, kids flexed their wrists tracing big and small number five. This is a good exercise for developing their fine motor skills.
whitefieldspreschools.com/2017/01/22/chugga-chugga-choo-c...
Practitioner playing with child.
Mawozini Crèche is in phase 2 repairs.
Proposed work at the centre includes:
- Additional classroom - the existing facility caters for 46 children, the attendance is just more than the number of children catered for in the existing facility;
- Repairs: the existing is in a relatively good condition, a door needs replacement, 4 locksets need replacing, a number of window panes need replacing, the apron requires repair.
- Fencing - the facility is fenced, however, the area is insufficient, particularly if an additional classroom is required. It is proposed that the area is extended and that the fence is repaired where required.
- Health & Safety: The centre also requires a fire extinguisher, first aid box, safety signage, and a fenced waste pit.
- Toilet facility: The centre has 2 toilet facilities which are both in a relatively poor condition. It is proposed that the face brick facility is repaired and used as a teacher’s toilet, and a new small facility built for the learners, with a new disabled unit included.
- A gutter downpipe is required.
- Play equipment: The facility has play equipment. Some of this equipment is in need of repair. A new shade cloth covering for the play area is required.
- Estimate costs for repairs: R 334 570
Practitioner with child.
In picture: Miss Celiwe Mzila.
Mawozini Crèche is in phase 2 repairs.
Proposed work at the centre includes:
- Additional classroom - the existing facility caters for 46 children, the attendance is just more than the number of children catered for in the existing facility;
- Repairs: the existing is in a relatively good condition, a door needs replacement, 4 locksets need replacing, a number of window panes need replacing, the apron requires repair.
- Fencing - the facility is fenced, however, the area is insufficient, particularly if an additional classroom is required. It is proposed that the area is extended and that the fence is repaired where required.
- Health & Safety: The centre also requires a fire extinguisher, first aid box, safety signage, and a fenced waste pit.
- Toilet facility: The centre has 2 toilet facilities which are both in a relatively poor condition. It is proposed that the face brick facility is repaired and used as a teacher’s toilet, and a new small facility built for the learners, with a new disabled unit included.
- A gutter downpipe is required.
- Play equipment: The facility has play equipment. Some of this equipment is in need of repair. A new shade cloth covering for the play area is required.
- Estimate costs for repairs: R 334 570
Child on swing.
Mawozini Crèche is in phase 2 repairs.
Proposed work at the centre includes:
- Additional classroom - the existing facility caters for 46 children, the attendance is just more than the number of children catered for in the existing facility;
- Repairs: the existing is in a relatively good condition, a door needs replacement, 4 locksets need replacing, a number of window panes need replacing, the apron requires repair.
- Fencing - the facility is fenced, however, the area is insufficient, particularly if an additional classroom is required. It is proposed that the area is extended and that the fence is repaired where required.
- Health & Safety: The centre also requires a fire extinguisher, first aid box, safety signage, and a fenced waste pit.
- Toilet facility: The centre has 2 toilet facilities which are both in a relatively poor condition. It is proposed that the face brick facility is repaired and used as a teacher’s toilet, and a new small facility built for the learners, with a new disabled unit included.
- A gutter downpipe is required.
- Play equipment: The facility has play equipment. Some of this equipment is in need of repair. A new shade cloth covering for the play area is required.
- Estimate costs for repairs: R 334 570