New Village Aerials 1/17/14

During this phase of construction on New Village:

 

- All roofing operations were completed.

- Progression of cementitious siding

- Masonry veneer work at Building #5 was in progress

- Interior drywall operations at Buildings #1 and #2

- Finishes being installed at Building #1

 

For more about this project visit www.tritecrealestate.com