View allAll Photos Tagged sitework
Granada Village Shopping Center Redevelopment (Building A1 TJ Maxx Roof Construction - 2012-01-12) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Phase 1 Traffic Circle Sitework Construction - 2011-07-28) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building B Stein Mart Facade Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building B Stein Mart Facade Construction - 2012-01-31) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Rite Aid Interior Construction - 2011-09-08) - Granada Hills, CA. Urban One www.urbanone.com.
Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.
Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.
Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.
Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.
Granada Village Shopping Center Redevelopment (Pad L Interior Construction - 2012-02-20) - Granada Hills, CA. Urban One www.urbanone.com.
Refurbishment of the existing church and bell-tower together with the construction of an extension to the existing sacristy and repairs and alterations to boundary walls together with associated siteworks.
Full QS service, traditional procurement. The challenge for this project was to meet the strict budget. We provided a cost plan to guide the design, regular cost checks to control cost during design development, a Bills of Quantities and careful monitoring to control cost during construction; contract and tender documentation for main works; regular predictive cost reports.
Granada Village Shopping Center Redevelopment (Phase 2 Sitework Construction - 2012-03-06) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Pad L Interior Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.
Voor de sporthal staan twee uitvoerders in overleg. Helmen op, handen in de zakken, even stilstaan in de stroom van het werk. Op de achtergrond tekent de ronde gevel zich af, terwijl binnen al materialen klaarstaan voor de volgende fase. Een klein moment van afstemming, midden in de bouwpraktijk.
🇬🇧 In front of the sports hall, two site managers pause for a brief discussion. Helmets on, hands in pockets, a short standstill within the ongoing flow of work. Behind them, the curved façade takes shape, while materials inside await the next phase. A quiet moment of coordination in the midst of construction.
Granada Village Shopping Center Redevelopment (Building A1 TJ Maxx Roof Construction - 2012-01-12) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Phase 1 Completion - 2011-09-08) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (HomeGoods Interior Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A1 Roof Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building B Stein Mart Facade Construction - 2012-01-27) - Granada Hills, CA. Urban One www.urbanone.com.
Robert Morris reclaimed a 4 acre gravel pit into a work of art.
"The first thing that seems rather bizarre to me. That is, that the selling point was, that the art was going to cost less than restoring the site to its "natural condition." What are the implications of that kind of thinking...that art should be cheaper than nature? Or that siteworks can be supported and seen as relevant by a community only if they fulfill a kind of sanitation service?
The most significant implication of art as land reclamation is that art can and should be used to wipe away technological guilt. Do those sites scarred by mining or poisoned by chemical now seel less like the entropic liabilities of ravenous and short-sighted industry and more like long-awaited aesthetic possibilites? Will it be a little easier in the future to rip up the landscape for one last shovelful of non-renewable energy source if an artist can be found (cheap, mind you) to transform the devastation into an inspiring and modern work of art? Or anyway, into a fun place to be? We, at the very least, into a tidy, mugger-free park." (Fragile Ecologies, 1992)
The appearance of Morris's earthworks site is just a hole in the ground. From different angles, specifically from the bottom of the pit looking up the stairs, the view appears infinite.
Granada Village Shopping Center Redevelopment (Pad L Facade Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A2 Facade Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Granada Village Shopping Center Redevelopment (Building A3 & A4 Facade Construction - 2012-02-08) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A3 & A4 Facade Construction - 2012-01-27) - Granada Hills, CA. Urban One www.urbanone.com.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
uilding 1
Roof Trusses are 95% complete with sheathing 75% complete on the building.
Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.
Shingle and Flat Roof Installation is underway and 65% complete.
Building weather wrap is being installed and 90% complete.
Window Installation is underway and 75% complete.
Siding installation has started in the Courtyard.
Parking Garage Sprinkler systems is 75% complete.
Courtyard waterproofing prep is underway.
Building 2
Roof Sheathing is complete.
Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.
Shingle and Flat Roof Installation is underway and 95% complete.
Building weather wrap is being installed and 95% complete.
Siding is underway on the South elevation and is 10% complete
Window Installation is underway and 85% complete.
Building 3
Wood framing has commenced.
Building 4
Foundation is 100% complete
Elevator shaft construction is complete
Underground Plumbing Rough is 65% complete
Underground Electrical Rough is 75% complete
Building 5
Foundation, underground utilities and slab is complete.
Progress pending framing start forecasted to start in November, 2018.
Building 6
Siding is complete.
Insulation is complete
Drywall installation is complete.
Site curbs are complete.
Painting is underway
Tile installation is underway.
Interior door and trim is underway.
Sitework
Curb formwork and installation is 90% complete on Mill Road
Starting to set building site to final subgrade
Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete
Damproofing and backfill has started.
Granada Village Shopping Center Redevelopment (Phase 1 Pervious Pavers Sitework Construction - 2011-07-21) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Sprouts Grand Opening - 2011-09-08) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Phase 2 Sitework Construction - 2012-02-08) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A1 - TJ Maxx Facade Construction - 2011-10-06) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A3 & A4 Facade Construction - 2012-02-24) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.
Granada Village Shopping Center Redevelopment (Pad L Facade Construction - 2012-02-24) - Granada Hills, CA. Urban One www.urbanone.com.