This March at New Village the following major construction items were underway:

 

Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.

 

Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade

 

Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation

 

Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation

 

Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.

 

The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.

Middle Temple Lane, The City, London.

During this phase of construction we are working on:

- Completion of cementitious siding at Building #3

- Progression of cementitious siding at Building #4

- Masonry veneer work at Building #5 is nearing completion on South elevation and progressing on East Elevation

- Interior drywall operations at Buildings #5

- Finishes being installed at Building #2

- Main Utility Connections taking place

- Exterior courtyard planter walls being installed at Building #1

- Archways at N. Ocean being finished

thought i'd document this cute relic before it gets turned into a bank

The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.

During this phase of construction we are working on:

- Completion of cementitious siding at Building #3

- Progression of cementitious siding at Building #4

- Masonry veneer work at Building #5 is nearing completion on South elevation and progressing on East Elevation

- Interior drywall operations at Buildings #5

- Finishes being installed at Building #2

- Main Utility Connections taking place

- Exterior courtyard planter walls being installed at Building #1

- Archways at N. Ocean being finished

The New Village at Patchogue project has progressed nicely beyond 90% of all subgrade structural features and about 60% of the elevated structural post-tension slab work is completed or in progress. Building 1 spearheads the vertical rise with two levels currently framed and Masonry construction rising above the wood framing. Building 2 will under way with its first floor of wood framing by the end of April 2013. Mechanical, Electrical and Plumbing trades have been coordinating with ongoing structural components in all buildings as the system installation needs progress, and installation of roughed out systems in sub grade and framed units is well under way.

 

External site improvements are partially placed while the installation of a major portion of subgrade sewer, power, communication and drainage systems that will serve the project are scheduled to commence shortly. By the end of May, the last section of connecting structural slab is expected at the crossover to Havens Avenue opposite Jennings and will complete the footprint for vertical construction at buildings 1, 2, 3 and 5. Building 4 is scheduled to start excavation at West side of the site (on Main Street) to make way for the foundation at the last structure in the project.

 

flat screen wall enclosure

bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,

Sheridan&Co designed and installed a premium retail site for Urban Decay in House of Fraser.

During this phase of construction we are working on:

- Completion of cementitious siding at Building #3

- Progression of cementitious siding at Building #4

- Masonry veneer work at Building #5 is nearing completion on South elevation and progressing on East Elevation

- Interior drywall operations at Buildings #5

- Finishes being installed at Building #2

- Main Utility Connections taking place

- Exterior courtyard planter walls being installed at Building #1

- Archways at N. Ocean being finished

where the box shoe and plex box will go

bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,

Aerial photographs of the construction of the New Village Development.

 

For more information on this project please visit www.newvillagepatchogue.com

For more information about TRITEC please visit www.tritecrealestate.com

Store design by SKELA STUDIO: www.skelastudio.com

See all of the photos here: ourdream.smugmug.com/Commercial/MacGregor-MacDuff-Prestwick

For a professional Commercial photographer book Lee Live: Photographer - visit: www.leelivephotographer.com/

Duo Dickinson's (en.wikipedia.org/wiki/Duo_Dickinson) design for retail space along the Boston Post Road (Rt 1). See flic.kr/s/aHBqjzH2Jo for more of my images of this structure.

1 2 ••• 28 29 31 33 34 ••• 79 80