View allAll Photos Tagged retailspaces
During this phase of construction on New Village:
- All roofing operations were completed.
- Progression of cementitious siding
- Masonry veneer work at Building #5 was in progress
- Interior drywall operations at Buildings #1 and #2
- Finishes being installed at Building #1
For more about this project visit www.tritecrealestate.com
Christchurch's Re:START Mall on my walk around the city to catch up on events. February 7, 2015 Christchurch New Zealand.
Re:START is an outdoor retail space consisting of temporary buildings made from shipping containers. Opened in October 2011, Re:START has been steadily growing to approximately 40 retailers, a number of food caravans and a market on the weekend.
For More Info on the ReStart Mall: www.christchurchnz.com/destinations/christchurch/restart-...
bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,
bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,
New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.
Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.
Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.
Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.
bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,
bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,
The New Village at Patchogue project has progressed nicely beyond 90% of all subgrade structural features and about 60% of the elevated structural post-tension slab work is completed or in progress. Building 1 spearheads the vertical rise with two levels currently framed and Masonry construction rising above the wood framing. Building 2 will under way with its first floor of wood framing by the end of April 2013. Mechanical, Electrical and Plumbing trades have been coordinating with ongoing structural components in all buildings as the system installation needs progress, and installation of roughed out systems in sub grade and framed units is well under way.
External site improvements are partially placed while the installation of a major portion of subgrade sewer, power, communication and drainage systems that will serve the project are scheduled to commence shortly. By the end of May, the last section of connecting structural slab is expected at the crossover to Havens Avenue opposite Jennings and will complete the footprint for vertical construction at buildings 1, 2, 3 and 5. Building 4 is scheduled to start excavation at West side of the site (on Main Street) to make way for the foundation at the last structure in the project.
The New Village project is reaching another important milestone at the Building 1 structure, whereby roofing, windows and trim details are under way and expected to be completed by mid July. Building 5 is moving through a second level of wood frames panels and trusses atop the podium concrete deck. Building 2 is nearing the same progress as Building 5 where a second level of panels and trusses is moving West toward Building 3. At Buildings 2 & 3, a tremendous milestone marks the completion of the structural concrete deck that not only ties the buildings together, but also provides for the superstructure that supports utilities and the future crossover at Havens and Jennings. Building 3 also presents the completion of much of its West masonry wall where a “green screen” will provide the buildings siding and beauty. Building 4 has emerged from the soil with the footings, piers and frost walls. Columns at Building 3 and 4 are erected to support the final elevated decks for the project. Site Sewer is in place with much of the building storm connections in place. Subsurface vaults are set to make way for the eventual removal of overhead power lines and installation of underground power to the surrounding buildings.
bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,
New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.
Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.
Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.
Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.
The most spacious brand new one and two-bedroom apartment homes in Berkeley.
(Note: Artist Renderings)
New Village is strategically located at the “Four Corners” of the Village. New Village is a 4.87 acre mixed-use, multi-modal, residential redevelopment bounded by Main Street to the south, North Ocean Avenue to the east, Lake Street to the north and a parcel to the west of Havens Avenue. The site, sitting on a total of 3.28 acres of private land, consists of six parcels surrounding by a 1.68 acre Village parking lot. The project includes reshaping the existing Village property boundary while maintaining the overall acreage and parking count.
The entire project includes 291 residential apartment units and 36,149 square feet of restaurant and retail space. Additionally, the project will have a total of 509 parking spaces screened from the street beneath the residential buildings and in surface lots.
bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,