View allAll Photos Tagged retailspace
The W57 tetrahedron building at 625 West 57th Street, designed by Bjarke Ingels Group (BIG), offers 709 residential rental units and 45,000 square feet of commercial retail space (scheduled to open in early 2016)
This aerial photograph represents construction progress for the New Village project, a 291 unit mixed-use development, as of December 14, of 2012. The phase of the project includes the site and concrete foundation development progressing at Buildings 3, 5, and 1 which are the Westerly most and Easterly most portions of the structure. Structural mat slabs, ramps and perimeter foundation walls are progressing at the Building's 5 and 1 located along the East side of the site. The entire mat slab and perimeter foundation is complete at Building 3 along the West side of the site and the post tension elevated slab is 80 % complete at the same Building. The sub grade structure is being excavated for Building 2 (at center of site) and the subsurface waterproofing membrane is being installed at spread footing locations. Additional scope that is progressing at this time includes the Mechanical, Electrical and Plumbing scope that is being installed within and below slabs.
New Village at Patchogue project has almost completed construction of all structures in their vertical rise. Roof trusses are topping off Buildings 3 and 4 to the West while Buildings 2, 1, and 5 are fully roofed. Siding systems at Buildings 2 and 1 are very far along with trim details at Decks being completed. The building elevations present many different features and with much in place, the true charm of the buildings is becoming evident.
Exterior site features are being prepared to accommodate parking lot, sidewalk and landscape features and interior features are becoming a primary focus in the move toward completed buildings.
Exterior Brick and Stone are commencing at Building 5 while these features are nearing completion already at Buildings 1 and 2.
The interior of Building 1 is being trimmed, painted and tiled with cabinetry and floorcovering features moving forward as well. Building 2 is currently being sheetrocked and similar progress is soon to follow at Building 5.
This March at New Village the following major construction items were underway:
Building #1 and #2 – Courtyard Planter construction on exterior and on interior doing paint touch ups, final inspections and cleaning in advance of April 1 Tenant Move In.
Building #5 – Painting, Tile, Flooring installation and completion of exterior brick façade
Building #3 – Drywall and spackle operations, painting and floor tile, brick façade installation and siding installation
Building #4 – Mechanical, Electrical and Plumbing Rough In, Exterior siding installation
Sitework – finishing curb and sidewalk installations and brick paver installation has started. Preparations being made for final level of asphalt paving.
The old warehouse floors were polished and sealed, but keep their character. Duo Dickinson's (en.wikipedia.org/wiki/Duo_Dickinson) design for retail space along the Boston Post Road (Rt 1). See flic.kr/s/aHBqjzH2Jo for more of my images of this structure.
Built 2017 - 2022 Architects - Hariri Pontarini Architects .... Comprised of seven buildings, all linked by a glass-covered public retail podium — the Well offers more than four million square feet of office, residential, retail and leisure space.
One of the joys of long exposure is that you should get good blurr on people walking across the scene, but they didn't register on this 30s exposure. It makes the place look dead, as opposed to busy with Christmas shoppers.
bhiwandi property wala, property bazaar, bhiwandibazaar, www.ajmeria.com, Office, Premises, Retail Space, WAREHOUSING, Factory Indl.,Factory, Plot, Land, COMMERCIAL SPACE, Shop, Showrooms, for Bank, ATM, Retailing Branch, Call Centers, commercial premises, BPO, KPO, ,call centers premises, premises for school, collages, hospitals, coaching classes, IT SOFTWARE, PARK ZONE, GAMING ZONE, SPA, GYM, SALOON, garages, service station, workshop, Office Buildings, Training centers, hotels, hospitals, school, college, old age house Project,
Duo Dickinson's (en.wikipedia.org/wiki/Duo_Dickinson) design for retail space along the Boston Post Road (Rt 1). See flic.kr/s/aHBqjzH2Jo for more of my images of this structure.
Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.
Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.
Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.
Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.
Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.
Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.
Store owner Sarah Kaplan started her career as a buyer for Neiman Marcus' European Sportswear and eventually did the buying for Barney's Private Label Collection. She now uses her well-trained eye to do the buying for her Westport, CT store by traveling to Paris and the south of France six times a year, finding the best antiques from Bagues to Napoleon III. - MABelle
During this phase of construction on New Village:
- All roofing operations were completed.
- Progression of cementitious siding
- Masonry veneer work at Building #5 was in progress
- Interior drywall operations at Buildings #1 and #2
- Finishes being installed at Building #1
For more about this project visit www.tritecrealestate.com
Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.
Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.
Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.
Duo Dickinson's (en.wikipedia.org/wiki/Duo_Dickinson) design for retail space along the Boston Post Road (Rt 1). See flic.kr/s/aHBqjzH2Jo for more of my images of this structure.
New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.
Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.
Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.
Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.
Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.
Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.
Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.
Residents of Galveston Island are presented with a lifestyle that most people dream about, but are rarely lucky enough to experience in their lifetime.
With the perfect blend of vibrant energy and quaint charm, downtown Galveston is an ideal setting for those looking to live or work in a historic district that’s accessible, walk-able, and part of history
On any given weekend, it's not unusual to see live musical performances in the park, food and wine tastings, nature exhibits or evening ghost tours along the city streets, but it's the true beauty of the Victorian architecture that has been impeccably preserved by Mitchell Historic Properties that gives this area the unique character and ambiance it has become known for today.
Recognized for their quality workmanship and the stellar appearance of their buildings, Mitchell Historic Properties has proudly owned and operated commercial and residential properties in downtown Galveston for over 30 years, including one fourth of the buildings in The Strand National Historic Landmark District and Pier 21 along Galveston’s historic harbor.
From retail spaces that date as far back as the 1850's, to apartments or lofts with architectural detail that can only be found in historic buildings, Mitchell Historic Properties has what you need.
New Village is strategically located at the “Four Corners” of the Village. New Village is a 4.87 acre mixed-use, multi-modal, residential redevelopment bounded by Main Street to the south, North Ocean Avenue to the east, Lake Street to the north and a parcel to the west of Havens Avenue. The site, sitting on a total of 3.28 acres of private land, consists of six parcels surrounding by a 1.68 acre Village parking lot. The project includes reshaping the existing Village property boundary while maintaining the overall acreage and parking count.
The entire project includes 291 residential apartment units and 36,149 square feet of restaurant and retail space. Additionally, the project will have a total of 509 parking spaces screened from the street beneath the residential buildings and in surface lots.
Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.
Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.
Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.
Elevations on New Village at Patchogue’s Building 1 are now complete. Inside building 1, paint, tile and trim are nearly complete and cabinet and granite installations have begun on the 4th floor with floor. Roofing is complete on Buildings 2 and 5 and elevations are underway. Inside Building 2 Interior trades are completing rough plumbing, electric, fire sprinkler and HVAC.
Masonry shafts, stair towers and installation of 3rd floor panels are almost complete on buildings 3 and 4.
Ongoing site work includes the rigging of submersible transformers; parking lot curbs and site lighting being installed in phase 1. With colder weather approaching interior parking lot development and courtyard construction as well as completing the installation of all utilities to the buildings is a priority.