View allAll Photos Tagged Telehandlers

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

For more information on equipment and solutions from Finning visit www.finning.co.uk

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Rotten sleepers being carried away by the Telehandler.

 

January 2016.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Equipment used

Manitou Telehandler

3 ton Manitou Fork lift

15 ton Fork lift

Hino 7 ton Hiab truck

Reach Stacker

 

Four Containers arrived at location and preparation to un-stuff began. Oversized loads were inspected for damage in transit, a pre-determined lifting plan actioned. Steel.Steel beams were stacked on top of the cargo which meant that manual labor was needed to un-stuff each container prior to using the MHE.

 

Once the steel had been removed manually, pallet trucks and fork lifts made easy work of un-stuffing the containers and placing the cargoes in the designated unpacking area.

 

Each container presented a different challenge regarding the safest way to un-stuff the cargo to prevent any damage. Eight meter steel beams had to be manually un-stacked before the telehandler could reach into the containers and pull the individual pieces out.

 

CEA provided all plastic sheeting and tarpaulins made at our plastic production facilities in Laem Chabang, these would protect the new ground surface from heavy equipment damage whilst the operation was underway.

 

The oversized cargo was lifted out of the containers through the use of a Reach Stacker.

 

Each of the four containers presented their own individual difficulties for manual and mechanical un-stuffing, the CEA team improvised and adapted well to overcome each hurdle much to the delight of the client.

Description

Model: MMT80-W

Specs:

1.) Hydraulic controling, hydr. flow is 12.6GPM

2.) Tipping capacity: 794kgs

3.) Weight (with out bucket): 856kgs / 1887lbs

4.) Engine: Kohler, command pro. Gasoline engine original Honda engine, gasoline type (but the Honda engine delivery time is 3 months, we advise KOHLER engine..)

5.) Dimensions (with bucket): 2235mm(L)*1080mm(W)*1245mm(H) (its not under operating situations).

Many kinds of attachments optional

We are professional SKid Steer Loader,Track Loader,Wheel Loader,Backhoe Loader,Telehandler manufacturers and factory.We can produce SKid Steer Loader,Track Loader,Wheel Loader,Backhoe Loader,Telehandler according to your requirements.More types of SKid Steer Loader,Track Loader,Wheel Loader,Backhoe Loader,Telehandler wanted,please contact us right now!

 

www.wolverineloader.com

1 2 ••• 27 28 30 32 33 ••• 79 80