View allAll Photos Tagged sitework

Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.

Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.

Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.

Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.

 

Granada Village Shopping Center Redevelopment (Pylon Sign Construction - 2011-10-20) - Granada Hills, CA. Urban One www.urbanone.com.

Looking west exit drive and pedestrian sidewalk - Terminal 4 @ Port Everglades

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Granada Village Shopping Center Redevelopment (Rite Aid Facade Construction - 2011-09-08) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-26) - Granada Hills, CA. Urban One www.urbanone.com.

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.

Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.

Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.

Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.

 

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Granada Village Shopping Center Redevelopment (Petco Facade Construction - 2011-09-01) - Granada Hills, CA. Urban One www.urbanone.com.

Main Street art project: a big wall of slate where people can add their own artwork to this piece of art.

 

The 54-foot Community Chalkboard and Podium monument, located in front of the Charlottesville City Hall and adjacent to the civic amphitheatre in Charlottesville, Virginia, has been honored with two design awards for architectural excellence - a 2009 Silver Medal Rudy Bruner Award for Urban Excellence and a 2009 Inform Honor Award from the Virginia Chapter of the American Institute of Architects’ (AIA). Designed by architect Robert Winstead of SHW Group and landscape architect Pete O’ Shea of Siteworks, LLC, the interactive monument celebrates free expression and was built to honor the First Amendment of the United States Constitution.

 

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Trenholm State Community College is currently in the process of architecturally re-branding their Patterson Campus. Trenholm State Community College’s Automotive Collision Repair Program was moved from the Trenholm Campus to the Patterson Campus, and in doing so, will utilize an existing 18,727sf metal building/warehouse which was conducive for the collision repair area. Additional square footage was added to the building to encompass two classrooms, a resource room, offices, tool storage, and a paint shop. The paint shop consists of two new pre-fabricated paint booths, mixing station, and prep area A new façade was developed to enhance the overall appearance of the building. This building is the first of many to feature the new architectural style.

Trenholm State Community College’s Administration and Financial Aid Building project included a new metal retrofit roof and the renovation of an existing building that houses administration offices, financial aid and other student amenities as part of there “Student Success” center to allow for additional classrooms. The existing spaces were updated with new finishes and associated energy efficient mechanical, electrical, and plumbing work. A new entrance and sitework were designed to give a good first impression to students and administrators entering campus.

Trenholm State Community College purchased state of the art prefabricated welding booths for their welding program. However, the buildings electrical system could not accommodate the loads for the booths. Goodwyn, Mills and Cawood was hired to prepare the architecture and engineering drawings to allow the program to use their new welding stations.

Building B & Building D were renovations that include interior and exterior work, re-roofing, structural, mechanical, electrical, civil, site work, exterior lighting, new streets, repairs and alterations to existing streets and parking lots, landscaping, and sidewalks.

 

Granada Village Shopping Center Redevelopment (Building A1 Roof Construction - 2012-02-07) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Rite Aid Loading Dock Sitework Construction - 2011-07-28) - Granada Hills, CA. Urban One www.urbanone.com.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Granada Village Shopping Center Redevelopment (Exterior Decorative Carriage Lights - 2012-02-20) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Phase 2 Sitework Construction - 2011-09-08) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Petco Loading Dock Sitework Construction - 2011-07-28) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Pad L Facade Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Granada Village Shopping Center Redevelopment (Phase 1 Rite Aid Loading Dock Sitework Construction - 2011-07-21) - Granada Hills, CA. Urban One www.urbanone.com.

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Jobsite sign for Haskell at UCF's new Parking Garage VI ("H").

 

Photo taken on 08/03/10.

 

Visit underconstructionforever.com for more info and UCF construction photos.

Granada Village Shopping Center Redevelopment (Sprouts Grand Opening - 2011-09-08) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A1 - TJ Maxx Roof Replacement - 2011-10-14) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (R-3 Sidewalk Improvements - 2012-02-10) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building A1-A4 Rain Damage - 2012-01-24) - Granada Hills, CA. Urban One www.urbanone.com.

Granada Village Shopping Center Redevelopment (Building B Stein Mart Facade Construction - 2012-02-09) - Granada Hills, CA. Urban One www.urbanone.com.

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Granada Village Shopping Center Redevelopment (Building A3 & A4 Facade Construction - 2012-03-06) - Granada Hills, CA. Urban One www.urbanone.com.

uilding 1

Roof Trusses are 95% complete with sheathing 75% complete on the building.

Mechanical, Electrical, Plumbing rough in is underway on the 3rd and 4th floors and 50% complete.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 90% complete.

Window Installation is underway and 75% complete.

Siding installation has started in the Courtyard.

Parking Garage Sprinkler systems is 75% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Roof Sheathing is complete.

Mechanical, Electrical, Plumbing and Fire Sprinkler rough in is 40% complete at the 3rd floor and progressing up to the 4th floor.

Shingle and Flat Roof Installation is underway and 95% complete.

Building weather wrap is being installed and 95% complete.

Siding is underway on the South elevation and is 10% complete

Window Installation is underway and 85% complete.

 

Building 3

Wood framing has commenced.

 

Building 4

Foundation is 100% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 65% complete

Underground Electrical Rough is 75% complete

 

Building 5

Foundation, underground utilities and slab is complete.

Progress pending framing start forecasted to start in November, 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is complete.

Site curbs are complete.

Painting is underway

Tile installation is underway.

Interior door and trim is underway.

 

Sitework

Curb formwork and installation is 90% complete on Mill Road

Starting to set building site to final subgrade

Pump station Wet Well foundation walls have been poured and wall formwork for balance of building is 95% complete

Damproofing and backfill has started.

Electrical underground for new relocatable classrooms

Granada Village Shopping Center Redevelopment (Pad L Interior Construction - 2012-02-28) - Granada Hills, CA. Urban One www.urbanone.com.

The new sign and address is installed. Hopefully, we can start sitework next week.

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

Building 1

Wood Framing installation is complete.

Roof Trusses are moving forward at the Northside.

Mechanical, Electrical, Plumbing rough-in is underway on the 3rd and 4th floors.

Shingle and Flat Roof Installation is underway and 35% complete.

Building weather wrap is being installed and 40% complete.

Courtyard waterproofing prep is underway.

 

Building 2

Wood Framing installation is complete.

Roof Trusses are complete, and roof sheathing is moving forward and in progress on 85% of the building.

Mechanical, Electrical, Plumbing, and Fire Sprinkler rough-in is complete at the 2nd floor and progressing up to the 3rd floor.

Shingle and Flat Roof Installation is underway and 65% complete.

Building weather wrap is being installed and 30% complete.

 

Building 3

Underground Rough is 100% complete

The slab is poured and waiting for wood framing to commence.

 

Building 4

Foundation is 1000% complete

Elevator shaft construction is complete

Underground Plumbing Rough is 25% complete

Underground Electrical Rough is 50% complete

 

Building 5

Foundation, underground utilities, and the slab is complete.

Progress pending framing start forecasted to for October 2018.

 

Building 6

Siding is complete.

Insulation is complete

Drywall installation is underway and 50% complete.

Site curbs are being installed

 

Sitework

Curb formwork and installation has started on Mill Road

Setting building site to final subgrade

Pump station Wet Well foundation walls are poured, and the wall formwork for the balance of building is 25% complete

1 2 ••• 13 14 16 18 19 ••• 76 77