Mandovi Third Bridge progress 7.4.2015
2.2Km, 4 lane cable stayed bridge estimated cost 466/470 crores built by GSIDC.
will be ready in 2.5years after work order issued.
Bridge or flyover starting from Merces junction to Porvorim Pundalik nagar
PM Narendra Modi laid foundation stone or formal inauguration of the project on 14th June 2014
CM Parrikar now says - dt. 12.6.14
it will be ready in 20-24 months
All formalities/approvals done, soil testing will start soon and work will start Mid Sept. 2014
The bridge will be 15 meters higher than the existing two (which would be about 25mtr over the water level) to save mangroves etc
About 900 mtrs from Porvorim side, 600mtrs over the River and 700 mtrs panjim side.
The project includes flyover towards Ponda side.
Video 1: New Bridge, Jetty status 7.4.15
www.youtube.com/watch?v=I7x-JxWfwrQ
watch and compare this video report 2 years ago
Video 2: Jetty Renovation etc status 7.5.2013
www.youtube.com/watch?v=uMi_uRCkfyc
Mandovi Third Bridge progress 7.4.2015
2.2Km, 4 lane cable stayed bridge estimated cost 466/470 crores built by GSIDC.
will be ready in 2.5years after work order issued.
Bridge or flyover starting from Merces junction to Porvorim Pundalik nagar
PM Narendra Modi laid foundation stone or formal inauguration of the project on 14th June 2014
CM Parrikar now says - dt. 12.6.14
it will be ready in 20-24 months
All formalities/approvals done, soil testing will start soon and work will start Mid Sept. 2014
The bridge will be 15 meters higher than the existing two (which would be about 25mtr over the water level) to save mangroves etc
About 900 mtrs from Porvorim side, 600mtrs over the River and 700 mtrs panjim side.
The project includes flyover towards Ponda side.
Video 1: New Bridge, Jetty status 7.4.15
www.youtube.com/watch?v=I7x-JxWfwrQ
watch and compare this video report 2 years ago
Video 2: Jetty Renovation etc status 7.5.2013
www.youtube.com/watch?v=uMi_uRCkfyc