Retail Facility Construction - Banana Republic
Gray-I.C.E. Builders was selected by Gap, Inc. for a 6,700 s.f. open store phased remodel project at their Banana Republic Glendale, California location.
The scope included new floors, cash wrap, feature walls and new paint. In order to have as little disruption as possible to the on-going business, the Gray-I.C.E. team worked nights to execute the project within the 5 week timeframe.
Retail Facility Construction - Banana Republic
Gray-I.C.E. Builders was selected by Gap, Inc. for a 6,700 s.f. open store phased remodel project at their Banana Republic Glendale, California location.
The scope included new floors, cash wrap, feature walls and new paint. In order to have as little disruption as possible to the on-going business, the Gray-I.C.E. team worked nights to execute the project within the 5 week timeframe.