Charles at Fordingbridge
Internals complete
- Erection of sustainable glulaminated timber frame – 2 days
- Internal steel work – 1 day
- Installation of highly insulated wall cladding. – 2 days
- Installation of highly insulated roof cladding. – 2 days
- Installation of EPDM rubber roof membrane – 1 day
- Installation of gutters and flashings. – 2 days
- Laying of under floor heating system, installation of air sourced heat pump and screed.
- Installation of triple glazed, argon filled low emission windows and external doors.
- Carpentry first fix - erection of stud walling.
- Electrical and plumbing first fix – electrical wiring and plumbing pipes installed.
- Plasterboard wall lining
- Carpentry second fix – architraves, internal doors and skirtings fitted.
- Painting and decorating
- Electrical and mechanical second fix – lighting, sockets and switches installed.
- Plumbing second fix - Sanitary ware installed.
- Installation of floor covering.
- Snagging
- Handover
Internals complete
- Erection of sustainable glulaminated timber frame – 2 days
- Internal steel work – 1 day
- Installation of highly insulated wall cladding. – 2 days
- Installation of highly insulated roof cladding. – 2 days
- Installation of EPDM rubber roof membrane – 1 day
- Installation of gutters and flashings. – 2 days
- Laying of under floor heating system, installation of air sourced heat pump and screed.
- Installation of triple glazed, argon filled low emission windows and external doors.
- Carpentry first fix - erection of stud walling.
- Electrical and plumbing first fix – electrical wiring and plumbing pipes installed.
- Plasterboard wall lining
- Carpentry second fix – architraves, internal doors and skirtings fitted.
- Painting and decorating
- Electrical and mechanical second fix – lighting, sockets and switches installed.
- Plumbing second fix - Sanitary ware installed.
- Installation of floor covering.
- Snagging
- Handover