Internals complete

- Erection of sustainable glulaminated timber frame – 2 days

- Internal steel work – 1 day

- Installation of highly insulated wall cladding. – 2 days

- Installation of highly insulated roof cladding. – 2 days

- Installation of EPDM rubber roof membrane – 1 day

- Installation of gutters and flashings. – 2 days

 

- Laying of under floor heating system, installation of air sourced heat pump and screed.

- Installation of triple glazed, argon filled low emission windows and external doors.

- Carpentry first fix - erection of stud walling.

- Electrical and plumbing first fix – electrical wiring and plumbing pipes installed.

- Plasterboard wall lining

- Carpentry second fix – architraves, internal doors and skirtings fitted.

- Painting and decorating

- Electrical and mechanical second fix – lighting, sockets and switches installed.

- Plumbing second fix - Sanitary ware installed.

- Installation of floor covering.

 

- Snagging

 

- Handover

 