Location: Imlay City, MI on the Canadian National Flint Subdivision formerly Grand Trunk Western RR ~ Maintenance took place in fall of 2020 program highlights included:

 

•Replacement of approximately 5 miles of rail

•Installation of over 105,000 new railroad ties

•Rebuilds of 24 road crossing surfaces

•Maintenance work on of bridges, level crossings,

culverts, signal systems and other track infrastructure