HARDWARE INSTALLATION AND SPACE
Before Conducting the Site Survey; homework on the provided IBM Pre-requisitions were given to us as the parameters for site selection. On the basis of it I have prepared a single layout and also communicated with the client for their information. So that we all are on the same page. In this way we have developed a clear understanding for the requirement of Site Preparation. (Feb- 2010)
Hardware Delivery was started on March 31, 2010 and completed on 12th April 2010 in coordination with Operations and Logistic Teams in parallel to Power Work on other remaining sites.
HARDWARE INSTALLATION AND SPACE
Before Conducting the Site Survey; homework on the provided IBM Pre-requisitions were given to us as the parameters for site selection. On the basis of it I have prepared a single layout and also communicated with the client for their information. So that we all are on the same page. In this way we have developed a clear understanding for the requirement of Site Preparation. (Feb- 2010)
Hardware Delivery was started on March 31, 2010 and completed on 12th April 2010 in coordination with Operations and Logistic Teams in parallel to Power Work on other remaining sites.