New Village September 13 2013

New Village at Patchogue elevation on Building 1 is nearly complete, the siding and roofing details, along with the start of brick veneer, are substantially complete. Building 2 is nearing the same progress as Building 5 whereby roofing sheathing is capping the building. Buildings 2 and 5 are ready for roofing. Buildings 3 has started the installation of 2nd floor panels along with the rise of masonry shafts at stairs and elevators. Building 4 has completed the last of the structural elevated slabs on the projects and panels are laid out and ready for installation.

 

Site Sewer and storm drainage is largely completed. Subsurface vaults are set at all 6 locations and make way for the redirection of power and communication services.

 

Interior trades are completing roughing at plumbing, electric, fire sprinkler and HVAC while sheetrock, and interior finishes follow behind.

 

Progressive accomplishments will be evident within the next month or two where Buildings 3 and 4 will present vertical accomplishment in the framed state. Additionally, the project will soon have external sidewalk, asphalt and curb definitions within the project site layout. LIPA will be moving toward providing a form of permanent power and interior spaces will be achieving a more refined finish.

 

647 views
0 faves
0 comments
Uploaded on September 24, 2013
Taken on September 13, 2013