TRITEC Projects
New Village Aerials taken April 16
The New Village at Patchogue project has progressed nicely beyond 90% of all subgrade structural features and about 60% of the elevated structural post-tension slab work is completed or in progress. Building 1 spearheads the vertical rise with two levels currently framed and Masonry construction rising above the wood framing. Building 2 will under way with its first floor of wood framing by the end of April 2013. Mechanical, Electrical and Plumbing trades have been coordinating with ongoing structural components in all buildings as the system installation needs progress, and installation of roughed out systems in sub grade and framed units is well under way.
External site improvements are partially placed while the installation of a major portion of subgrade sewer, power, communication and drainage systems that will serve the project are scheduled to commence shortly. By the end of May, the last section of connecting structural slab is expected at the crossover to Havens Avenue opposite Jennings and will complete the footprint for vertical construction at buildings 1, 2, 3 and 5. Building 4 is scheduled to start excavation at West side of the site (on Main Street) to make way for the foundation at the last structure in the project.
New Village Aerials taken April 16
The New Village at Patchogue project has progressed nicely beyond 90% of all subgrade structural features and about 60% of the elevated structural post-tension slab work is completed or in progress. Building 1 spearheads the vertical rise with two levels currently framed and Masonry construction rising above the wood framing. Building 2 will under way with its first floor of wood framing by the end of April 2013. Mechanical, Electrical and Plumbing trades have been coordinating with ongoing structural components in all buildings as the system installation needs progress, and installation of roughed out systems in sub grade and framed units is well under way.
External site improvements are partially placed while the installation of a major portion of subgrade sewer, power, communication and drainage systems that will serve the project are scheduled to commence shortly. By the end of May, the last section of connecting structural slab is expected at the crossover to Havens Avenue opposite Jennings and will complete the footprint for vertical construction at buildings 1, 2, 3 and 5. Building 4 is scheduled to start excavation at West side of the site (on Main Street) to make way for the foundation at the last structure in the project.