Boring Machine
This the business end of one of the TBM (Tunnel Boring Machine) in Brisbane drilling a hole under the river, which will allow all those southerners that have moved to Queensland and are clogging up our roads, to move back to their own state more quickly.
This is the 21st Century solution to digging a hole.
This is a huge machine that bores and lines the hole with concrete as it moves forward. The excavated material is fed along a huge conveyor that removes it to holding tanks before dropping into trucks for disposal.
Some facts
Number of TBMs on the project Two, custom-built
Length 253m
Diameter 12.4m
Weight 4000 tonnes
Electrically powered by 4.2 mega watts
Cost $50 million each
Manufacturer German company Herrenknecht
Made from Steel
Number of rotating cuttters 77
Type of cutters 19-inch tungsten tipped discs
Advance rate 20m p/day
Number of precast segments needed to line the entire tunnel 37,000
Number of people operating each TBM 21 per shift
The North-South Bypass Tunnel project is approximately 6.8 kilometres in length from end to end and includes a 4.8 kilometre tunnel as well as associated road connections. The Project also includes a range of urban enhancements to surrounding suburbs. The NSBT is expected to open in the second half of 2010.
How boring is that.
For 7 Days of Shooting, Machines theme.
Boring Machine
This the business end of one of the TBM (Tunnel Boring Machine) in Brisbane drilling a hole under the river, which will allow all those southerners that have moved to Queensland and are clogging up our roads, to move back to their own state more quickly.
This is the 21st Century solution to digging a hole.
This is a huge machine that bores and lines the hole with concrete as it moves forward. The excavated material is fed along a huge conveyor that removes it to holding tanks before dropping into trucks for disposal.
Some facts
Number of TBMs on the project Two, custom-built
Length 253m
Diameter 12.4m
Weight 4000 tonnes
Electrically powered by 4.2 mega watts
Cost $50 million each
Manufacturer German company Herrenknecht
Made from Steel
Number of rotating cuttters 77
Type of cutters 19-inch tungsten tipped discs
Advance rate 20m p/day
Number of precast segments needed to line the entire tunnel 37,000
Number of people operating each TBM 21 per shift
The North-South Bypass Tunnel project is approximately 6.8 kilometres in length from end to end and includes a 4.8 kilometre tunnel as well as associated road connections. The Project also includes a range of urban enhancements to surrounding suburbs. The NSBT is expected to open in the second half of 2010.
How boring is that.