Load Two & Three - Day Four (40)

Prepairing to leave the abnormal load bay at Tot Hill for the 2nd leg of the 2nd journey. This layby was previously neglected and in co-operation with the police and council, we were able to secure this layby for the duration of the project. The layby was cleared by the council who had to remove about 10 tons of soil that they had dumped in front of the gates to prevent the layby being occupied. After the project is complete, the layby will be returned to its previous state. The UK transport project planning, permits & escorts was by Teahan Convoi Service. This load was escorted by Teahan, Convoi Assist, RVT & Hampshire Police.